There was an information session by hok yesterday for the Salt Lake International Airport Redevelopment discussing the phases and opportunities for local firms.
Page 12 of the presentation shows the Project timeline:
2012 - Complete Environmental Assessment; Finalize plan of execution, Conduct public outreach
2013 - Initiate Schematic Design
2014 - Begin construction of Rental Car Service Facilities (complete in 2015)
2015 - Begin construction of South Concourse West and Terminal
2016 - Begin construction of New Parking Garage
2017 - Begin construction of Terminal Roadway System
2018 - Open Terminal, South Concourse West, and Parking Garage
2019 - Demolish Terminals 1 & 2 and Existing Parking Garage, Begin construction of South Concourse East
2020 - Occupy gates on south side of South Concourse East
2021 - Demolish existing connectors; Construct apron on north side of South Concourse East
2022 - Occupy gates on north side of South Concourse East
2022-2026 - Renovate existing Concourses B, C, & D
The hok presentation slides can be downloaded here:
http://slcia.hok.com/,
SLCIA - Terminal Redevelopment Information Session, May 1, 2013