Quote:
Originally Posted by Dado
Am I missing something? Is Woodroffe Ave Public School at risk of running out of students any time soon? Because that sure would be odd for a school with a few portables out back.
And closing down libraries and the Carlingwood parkade? Why? For what it's worth, the YMCA is closing anyway.
I get the appeal of running the line south to Carlingwood, but why all this other activity? The City has never been too keen on directing development itself anyway - witness the Lansdowne debacle.
If I recall, Richard Eade proposed running the line along Lockhart and then through the Carlingwood property between the mall and the parkade. That's all that you really need to do to get the line south to Carling - a little bit of land trimming along the west side of Lockhart and that's about it.
|
Lockhart would be doable, although the ROW would need to be wider. If the YMCA is closed, there is a bit of extra room. Running it along Woodroffe would force interference with private residences, which is not a viable solution IMO. Maybe tunnel the whole section with an underground station at Carlingwood? How much extra would that cost though compared to the New Orchard route? (Note that ridership would surely be higher.)
The library would probably be better located within Carlingwood though where traffic is much heavier, and could easily take an expanded position.
Basically, I see 4 options to carry it through Carlingwood:
1) Surface alignment, expropriate some properties between Lockhart and Woodroffe. Requires relocating the schools.
2) Surface alignment, via Lockhart. Less expropriation but closer to the residential area.
3) Tunnel beneath entire area, with underground station at Carlingwood.
4) Elevated guideway in area, presumably via Lockhart.
In options 1 to 3, a tunnel beneath Carling is required to connect to Lincoln Fields, and in option 4, the elevated guideway continues.