What's that site preparation for if its construction hasn't been yet approved?? Could you please explain???
|
It's just a formality. All building work, whether new, alteration, or demo, requires a building permit. The buildings department has to certify that everything is in order before you are granted a permit. If it is denied, that means something was not in order. Doesn't mean you can't do the work, it means you can't do the work until you get the permit. The DOB also has the power to shut sites down, even if you have your building permit, if rules are not being followed or until things are put in order. The One57 site still has a partial stop work order. Building plans are often revised, and new permits reflect changes.
Site preparation on new buildings begins regardless because its only a matter of
when you get the permit, not
if.