Beginning May 6, Lorne Street between 11th Avenue and 12th Avenue will be closed for construction. The construction is scheduled for completion by mid October. The 12th Avenue intersection will be closed for the duration of the construction, with the 11th Avenue intersection also closed for three weeks in August or September.
While the construction may cause some inconvenience for drivers, it will allow for important upgrades. The project includes:
- Replacing the road structure with a concrete road so Lorne Street will have the structural capacity to carry Transit routes.
- Water, storm and domestic sewer upgrades.
- Sidewalk, curb and gutter replacement and landscaping enhancements.
- Street light replacement.
- Fiber optics and communication cable relocation.
- Potential SaskEnergy gas line work.
- New SaskPower duct bank to increase future capacity for growth.
- Traffic signal installation.
Traffic will be closed throughout the construction, with detours and signage in place. Transit buses will follow detours and will be rerouted.