Contractor says city shares blame for one-month delay in project
By David Hutton, The StarPhoenix
June 29, 2012 9:17 AM
The contractor in charge of the design and construction of the $300-million Circle Drive south project says the City of Saskatoon is partly responsible for delays that will see the project open one month late.
Bad weather has put the project behind, but there were land acquisition delays at the start of the project and extra work added by the city, said a statement from Graham-Flatiron, the joint venture leading the project.
There have been "numerous delays," Graham-Flatiron's assistant project manager Jorey Deml said in an email statement.
"(We have) experienced numerous delays on the project contributing to the potential late delivery of the Circle Drive south project," he said. "These delays include the weather event in 2010, land procurement delays at the start of the project by the city, weather delays in May and June of 2012, extra work added throughout the life of the project and late review of drawings by the city. [...]
Read more:
http://www.thestarphoenix.com/Contractor...e+month+delay+project/6858916/story.html