HomeDiagramsDatabaseMapsForum About
     

Go Back   SkyscraperPage Forum > Discussion Forums > Buildings & Architecture > Completed Project Threads Archive


    One World Trade Center in the SkyscraperPage Database

• Building Data Page   • Comparison Diagram   • New York Skyscraper Diagram

• Map Location
• New York Projects & Construction Forum

 

 
Thread Tools Display Modes
     
     
  #19381  
Old Posted Jan 23, 2012, 4:12 AM
CarlosV's Avatar
CarlosV CarlosV is offline
 
Join Date: Sep 2003
Posts: 3,820
^^^
nope....i got that from my living room :


DSC_5184 copy by Ceva321, on Flickr

Last edited by CarlosV; Jan 23, 2012 at 11:05 PM.
     
     
  #19382  
Old Posted Jan 23, 2012, 6:29 AM
N0rthcar0lina N0rthcar0lina is offline
 
Join Date: Jan 2007
Posts: 55
Quote:
Originally Posted by CarlosV View Post
^^^
nope....i got that from my living room
I am extremely jealous.
     
     
  #19383  
Old Posted Jan 23, 2012, 8:12 AM
Zapatan Zapatan is offline
 
Join Date: Aug 2009
Posts: 6,852
Awesome shot!

But the lack of new still is worrying
     
     
  #19384  
Old Posted Jan 23, 2012, 3:08 PM
crewex crewex is offline
 
Join Date: Jan 2012
Posts: 46
Construction restart

It takes approx one week to add the steel for a floor. Current top out is scheduled for sometime in April. Assuming they are still going to complete in April there is more than enough time to do so. There are 16 weeks until the end of april, and 14 floors.

That means, that as long as steel starts going on again anytime in the next 2 weeks that they are still on schedule. SOOOOO.........you guys start wringing your wrist and pacing back and forth in about 2 weeks. Currently it's still going according to plan.

Plus construction will increase in speed now that the days are getting longer and warmer.
     
     
  #19385  
Old Posted Jan 23, 2012, 4:20 PM
sterlippo1 sterlippo1 is offline
 
Join Date: Aug 2010
Posts: 1,266
Quote:
Originally Posted by crewex View Post

that the days are getting warmer.
they are ?
     
     
  #19386  
Old Posted Jan 23, 2012, 4:56 PM
Roadcruiser1's Avatar
Roadcruiser1 Roadcruiser1 is offline
 
Join Date: Jun 2010
Posts: 2,117
Quote:
Originally Posted by crewex View Post
It takes approx one week to add the steel for a floor. Current top out is scheduled for sometime in April. Assuming they are still going to complete in April there is more than enough time to do so. There are 16 weeks until the end of april, and 14 floors.

That means, that as long as steel starts going on again anytime in the next 2 weeks that they are still on schedule. SOOOOO.........you guys start wringing your wrist and pacing back and forth in about 2 weeks. Currently it's still going according to plan.

Plus construction will increase in speed now that the days are getting longer and warmer.
Spring doesn't come to NYC till late March. We are still in late January.
     
     
  #19387  
Old Posted Jan 23, 2012, 5:20 PM
NewYorker2009 NewYorker2009 is offline
 
Join Date: Mar 2009
Posts: 293
Quote:
Originally Posted by crewex View Post
It takes approx one week to add the steel for a floor. Current top out is scheduled for sometime in April. Assuming they are still going to complete in April there is more than enough time to do so. There are 16 weeks until the end of april, and 14 floors.

That means, that as long as steel starts going on again anytime in the next 2 weeks that they are still on schedule. SOOOOO.........you guys start wringing your wrist and pacing back and forth in about 2 weeks. Currently it's still going according to plan.

Plus construction will increase in speed now that the days are getting longer and warmer.
What is your source to all this information? There are no more typical office floors anymore, only mechanical floors remain. Each mechanical floor will not take a week to do. It's almost February and they need to pack on an additional 200 plus feet before top out so April does not seem likely at this point no matter who your source is.
     
     
  #19388  
Old Posted Jan 23, 2012, 6:01 PM
crewex crewex is offline
 
Join Date: Jan 2012
Posts: 46
topout date

from http://www.lowermanhattan.info/construction/project_updates/freedom_tower_26204.aspx

*The following information was last updated on January 20, 2012.

Tower steel is now above floor 91. It is expected to top out by appx. April of 2012.
Facade installation is now above floor 66
Concrete is now being installed above floor 85
Installation of the 400-foot-tall antenna in spring 2012.
Spray-on fireproofing underway
Elevator shaft fit-out
Multiple cranes on site for steel and concrete installation
Both the south and north cores are now being erected as the structure rises
"Cocoon" safety system now in place around upper perimeter, to rise with structure
Utility installation and tie-ins
Crews are coordinating substructure construction while maintaining PATH service

Not that they havn't had some latency problems with this information, but it's been fairly accurate about projections for the past 5 or 6 months
     
     
  #19389  
Old Posted Jan 23, 2012, 6:02 PM
dchan's Avatar
dchan dchan is offline
 
Join Date: Dec 2007
Posts: 2,671
Quote:
Originally Posted by NewYorker2009 View Post
What is your source to all this information? There are no more typical office floors anymore, only mechanical floors remain. Each mechanical floor will not take a week to do. It's almost February and they need to pack on an additional 200 plus feet before top out so April does not seem likely at this point no matter who your source is.
I dunno. From what I've read of his posts, crewex seems to have experience in the field, so I would at least consider what he has to say.
     
     
  #19390  
Old Posted Jan 23, 2012, 6:22 PM
crewex crewex is offline
 
Join Date: Jan 2012
Posts: 46
steel stall

He is right though, some of the remaining floors are non standard, but the mechanical floors are double flloors, (correct me if i'm wrong at any point) so they can be allotted two weeks of time. One week to assemble the steel, one week we to drop in equipment (actually more than one week, from construction pictures at the top, it looks like they finish the decking for a floor 2 to 3 weeks after they do the steel.) And there is nothing that says they have to do all the decking for each floor if they are trying to lower (instead of drift) mechanical floor equipement in.



http://www.panynj.gov/wtcprogress/pdf/January-2012-wtcprogress-Newsletter.pdf
The newsletter doesn't mention a top out date which odd since investors probably read it (maybe they get a different mailing). but it does have a pretty detail that shows the rented regions of the building

I did send off an email or two to some of the communications officers. Even if they give us BS, at least we will have the official statement of the construction stall. Let's just hope it's part of the plan.

NOW, who knows what goes on a mechanical floor since I read that each floor will have it's own climate control system. So it's not like they will need a complex heating and cooling system up there, maybe it's elevators, water pumps, and bears, then that might explain the hold up.
     
     
  #19391  
Old Posted Jan 23, 2012, 6:41 PM
crewex crewex is offline
 
Join Date: Jan 2012
Posts: 46
warmer weather

Quote:
Originally Posted by sterlippo1 View Post
they are ?
Technically, even though it's still cold outside, YES the days are getting warmER on average and longer every day (many studies have shown that productivity has a positive relationship to temperate well lit conditions and sunlight exposure. But last I checked, March is before April so when I said that, I was being inclusive of all the time between now and top out. To be precise.

http://www.weather.com/weather/wxclimatology/monthly/graph/USNY0996
longer and warmer

www.nrel.gov/docs/fy02osti/30769.pdf
Lighting and temperature effects on productivity
     
     
  #19392  
Old Posted Jan 23, 2012, 7:04 PM
NewYorker2009 NewYorker2009 is offline
 
Join Date: Mar 2009
Posts: 293
Quote:
Originally Posted by crewex View Post
from http://www.lowermanhattan.info/construction/project_updates/freedom_tower_26204.aspx

*The following information was last updated on January 20, 2012.

Tower steel is now above floor 91. It is expected to top out by appx. April of 2012.
Facade installation is now above floor 66
Concrete is now being installed above floor 85
Installation of the 400-foot-tall antenna in spring 2012.
Spray-on fireproofing underway
Elevator shaft fit-out
Multiple cranes on site for steel and concrete installation
Both the south and north cores are now being erected as the structure rises
"Cocoon" safety system now in place around upper perimeter, to rise with structure
Utility installation and tie-ins
Crews are coordinating substructure construction while maintaining PATH service

Not that they havn't had some latency problems with this information, but it's been fairly accurate about projections for the past 5 or 6 months
Well I don't know how reliable www.lowermanhattan.info is because it says the Tower is now above floor 91 and they haven't even finished floor 90 yet lol. I really feel only the construction workers have the best idea when things will get done because they are building it so they will estimate based on weather, delays, etc. The Tower will be done when it's done that's all I can say. Going by an estimated date from that website is just not reliable enough for me. I think the top out date could be around May or June hopefully.
     
     
  #19393  
Old Posted Jan 23, 2012, 7:51 PM
NewYorkSkyline117 NewYorkSkyline117 is offline
 
Join Date: May 2011
Posts: 514
Quote:
Originally Posted by crewex View Post
from http://www.lowermanhattan.info/construction/project_updates/freedom_tower_26204.aspx

*The following information was last updated on January 20, 2012.

Tower steel is now above floor 91. It is expected to top out by appx. April of 2012.
Facade installation is now above floor 66
Concrete is now being installed above floor 85
Installation of the 400-foot-tall antenna in spring 2012.
Spray-on fireproofing underway
Elevator shaft fit-out
Multiple cranes on site for steel and concrete installation
Both the south and north cores are now being erected as the structure rises
"Cocoon" safety system now in place around upper perimeter, to rise with structure
Utility installation and tie-ins
Crews are coordinating substructure construction while maintaining PATH service

Not that they havn't had some latency problems with this information, but it's been fairly accurate about projections for the past 5 or 6 months
Btw this can't be accurate...there's no way the facade is just above floor 66. it's at least approaching a little over 70 no?
     
     
  #19394  
Old Posted Jan 23, 2012, 7:55 PM
Kevin Scott Koepke Kevin Scott Koepke is offline
 
Join Date: Oct 2010
Posts: 252

one world trade center, through the fog; 1/23/2012 by kevin scott koepke photography, on Flickr

Please do not repost, copy, or otherwise reproduce. Thank you.
     
     
  #19395  
Old Posted Jan 23, 2012, 10:25 PM
NYguy's Avatar
NYguy NYguy is offline
 
Join Date: Jul 2001
Posts: 57,298
     
     
  #19396  
Old Posted Jan 23, 2012, 11:31 PM
jd3189's Avatar
jd3189 jd3189 is offline
 
Join Date: Dec 2010
Posts: 6,895
Quote:
Originally Posted by NYguy View Post
Awesome photos.Should be near perfection before this year's up.
     
     
  #19397  
Old Posted Jan 24, 2012, 2:39 AM
sbarn sbarn is offline
 
Join Date: Feb 2004
Posts: 2,075
Quote:
Originally Posted by Otie View Post
Oldie...


World Trade Center from Rooftop of 250 Hudson Street, 5:30PM | Elevator View
Whats going on with that opaque area in the curtain wall on the left side of One World Trade??
     
     
  #19398  
Old Posted Jan 24, 2012, 4:23 AM
Kevin Scott Koepke Kevin Scott Koepke is offline
 
Join Date: Oct 2010
Posts: 252

exchange place; 1/23/2012 by kevin scott koepke photography, on Flickr

Do not repost, copy, or otherwise reproduce. Thank you.
     
     
  #19399  
Old Posted Jan 24, 2012, 6:32 AM
Inkoumori Inkoumori is offline
 
Join Date: Jan 2011
Posts: 358
^Great Shot!

That is the Katyn Memorial in Jersey City (A massacre of the Polish in WWII)

theepochtimes.com
     
     
  #19400  
Old Posted Jan 24, 2012, 2:25 PM
CarlosV's Avatar
CarlosV CarlosV is offline
 
Join Date: Sep 2003
Posts: 3,820
I can see clearly now...

I can see clearly now the fog is gone!

again, no erections on top...oh well....




DSC_5196 copy by Ceva321, on Flickr
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
 

Go Back   SkyscraperPage Forum > Discussion Forums > Buildings & Architecture > Completed Project Threads Archive
Forum Jump



Forum Jump


All times are GMT. The time now is 12:16 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.