Originally Posted by SLC Projects
Thanks skyguy for those renderings and link. Since I also work up at the airport I been hearing alot of rumors about the airport project. Alot of these rumors have been on going for years and years. Rumors such as "the airport expansion will begin in about two years and we will be in a new building." Well that was 8 years ago.  Now the latest I'm hearing is about 10-15 years from now we will be in a new building. Right now there looks to be alot of heavy work going on the West runway area. Not too sure what's all going on over there, but my guess is that it has something to do with the runway. Also I'm hearing rumors that ground has been broken on the south field for the new Car Rental lots. ( not sure if that's true or not. ) For years that area has been used for car rental overflow.
|
That's cool, I didn't realize you worked there too. We've probably seen each other several times and not known it. I work at airport operations (city job).
The project on the west runway is for construction of new de-ice pads so planes can de-ice right before takeoff instead of right after push back. This will save the airlines money by reducing the chance of having to de-ice more than one time because of longer than anticipated taxi times, etc. The airport is also finishing up a number of deice pads near the center runway this year and it should be operational for this winter. The airport is also constructing glycol (the main ingredient in de-ice fluid) reclamation tanks to save even more money so it can be-reused instead of wasted. Glycol is like $8-10 per gallon so you can see how expensive it can get to de-ice planes.
I know there has been talk for years about the redevelopment of the airport terminals, but a lot of things have come up over the last 15 years from 9/11 to airline bankrupcies to economic downturns, etc.
I agree a new terminal is long overdue, and the city is well aware of it. But they have to be delicate how they go about doing this. They can't alienate the tenants. Other airports have gone ahead with new expensive new terminals without airlines on board. These cities have lost a lot of service because of it and the airports are left with lots of debt.
From what I understand, Delta has given the airport its blessing for a new terminal as well as some upgrades to some of the current concourses which will eventually be torn down.
The SLC airport is in a good financial situation (among the best in the country) and is closely working with airlines to make sure any impact on them won't result in cutting service. SLC is already one of the cheapest major airports to do business at and airlines want to keep it that way. From what I understand, Delta has given the airport its blessing for a new terminal as well as some upgrades to some of the current concourses which will eventually be torn down. Its a long process but it will be worth it. In a way it is a good thing it is taking long, because the regulations for airport construction have changed this last decade and now the airport will be able to build the airport with these impacts in mind instead of having to patch up or band-aid it like most airports have done which usually detracts from its aesthetic appeal.
We will get our new terminal, but its going to be done in phases and we will continue to be making upgrades to the current terminal and concourses in the meantime. I would say we won't see the large brand new terminal complete for at least 5-8 years. Once finished, the basic layout will be similar to the depictions above.
Quote:
Originally Posted by SLCdude
I've seen renderings, but not these ones. Thanks!
I'm wondering what they would do about the Airport TRAX line. The terminal station is being built on the far eastern side of the airport, and it looks like the new airport would be built farther West. I'm assuming the straight line that leads directly to the center of the terminal in the renderings is light rail. UTA would have to scrap the existing rails and build new ones that lead directly to the terminal.
|
Once the new parking structure is built, there will be a new Trax station built in it. It will be an elevated station so it will be the same floor as the departure level (second floor).