Quote:
Originally Posted by frinkprof
^Nice photos. Good to see the structural work starting to take shape at Westbrook. You should post those on CP as well.
I haven't been on the project much lately so I haven't been able to witness its progress, or take photos to post here.
|
On CP now too. When the weather is better, I'll go for a photo walk. I have noticed that the tunnel segment has been completed further east of 37th Street towards 35th. It would be good to remove the temporary bridge on 37th, but they'll probably wait until the Spring to do that.
I noticed another change in traffic management as well. The amount of "green" time on 17th Ave has been increased. When I was waiting at 17th and 33rd St this morning, the wait time was much greater. Was probably changed as a result of the traffic issues experienced on Bow Trail recently.