Old Posted Mar 29, 2010, 5:31 PM
frinkprof's Avatar
frinkprof frinkprof is offline
Registered User
 
Join Date: Sep 2006
Location: The Gary
Posts: 4,865
Quote:
Originally Posted by Sir.Humphrey.Appleby View Post
^ I think some people talk of WLRT as taking the route it does instead of going to Mount Royal University as an example of a politician on the take, which is totally bogus. They then used 'legacy' in a facetious sense imply that the project is also for personal aggrandizement.

I am not sure where Klein came into this really...

I would ask people: would we ever get any project done if it wasn't for personal aggrandizement for politicians?
Right here:

Quote:
Originally Posted by Sir.Humphrey.Appleby View Post
Pushing NE before the NW or W was the legacy part, as it seems Klein pushed it to the front of the line.
Are you saying the NE LRT was a "legacy project" for Klein? If so, what do you mean by the term "legacy project" in that context?
     
     
  #282  
Old Posted Mar 29, 2010, 6:10 PM
MalcolmTucker MalcolmTucker is offline
Registered User
 
Join Date: May 2007
Posts: 11,625
Quote:
Originally Posted by frinkprof View Post
Right here:



Are you saying the NE LRT was a "legacy project" for Klein? If so, what do you mean by the term "legacy project" in that context?
I was responding to something above I believe, perhaps interpreted in from another concurrent thread, and Aegis and ferreths exchange
     
     
  #283  
Old Posted Mar 29, 2010, 6:28 PM
frinkprof's Avatar
frinkprof frinkprof is offline
Registered User
 
Join Date: Sep 2006
Location: The Gary
Posts: 4,865
^Ah yeah, I think I missed a step in the conversation or misattributed someone else's words to you.
     
     
  #284  
Old Posted Mar 29, 2010, 6:38 PM
fusili's Avatar
fusili fusili is offline
Retrofit Urbanist
 
Join Date: Sep 2007
Posts: 6,692
From what I heard, the NW line was delayed because the City thought they could get federal funding for it for the Olympics and therefore built the NE first. Kind of a sneaky move, but it makes sense. If the NW line was complete before the Olympic bid was won, the feds would not fund the NE line because it wouldn't have any benefit for the Olympics. Don't remember who I heard it from though.
     
     
  #285  
Old Posted Mar 29, 2010, 6:43 PM
Deepstar's Avatar
Deepstar Deepstar is offline
Registered User
 
Join Date: Mar 2007
Location: Canada
Posts: 6,291
Quote:
Originally Posted by fusili View Post
From what I heard, the NW line was delayed because the City thought they could get federal funding for it for the Olympics and therefore built the NE first. Kind of a sneaky move, but it makes sense. If the NW line was complete before the Olympic bid was won, the feds would not fund the NE line because it wouldn't have any benefit for the Olympics. Don't remember who I heard it from though.
Did the city end up getting any money from the Feds for the NW line?
     
     
  #286  
Old Posted Mar 29, 2010, 6:46 PM
frinkprof's Avatar
frinkprof frinkprof is offline
Registered User
 
Join Date: Sep 2006
Location: The Gary
Posts: 4,865
^In an economics class I took a few years ago, as an in-class exercise, we did a benefit/cost analysis on either the NE or NW LRT line, on the assumptions that were in place before it was built (I can't remember 100% whether it was the NE or the NW since it was some time ago, but I'm pretty sure it was the NE). At any rate, the benefits, excluding one were outweighed by the costs and the line was deemed unfeasible based on that. However, what tilted the scales the other way was the benefit of having the line in place for the Olympics. Remember, the Olympics were awarded in '81, so both the NE and NW lines were approved and started construction after this decision. Also, while the NW line was obviously more important for the Olympics (Athletes Village, Oval), the NE was also important (Max Bell Arena).

Of course, the instructor went on to say that the line and the LRT as a whole had since paid itself back because the benefits had outpaced their assumptions and estimates. Basically it has ended up as a bigger success than they had originally imagined.
     
     
  #287  
Old Posted Mar 29, 2010, 7:49 PM
SubwayRev's Avatar
SubwayRev SubwayRev is offline
Registered User
 
Join Date: Aug 2007
Location: Calgary
Posts: 445
Quote:
Originally Posted by frinkprof View Post
^I think we are getting hung up on what is meant by "legacy" and "vanity" projects, and mistaking one for the other. I think what SHA means is that the LRT built in the '80s (particularly NE LRT) is, in retrospect, Klein's legacy. I don't think at the time nor now, that the NE LRT was a vanity project though.
I think your right. I was reading into people's comments, although they didn't necessarily mean what I was reading. But, I think 'legacy' is the completely wrong word for this discussion. When I think legacy, I think of something closely associated with that person. Nobody thinks of Ralph Klein when they think of NE LRT or vice versa.

Quote:
Originally Posted by Sir.Humphrey.Appleby View Post
I would ask people: would we ever get any project done if it wasn't for personal aggrandizement for politicians?
So true.
     
     
  #288  
Old Posted Mar 29, 2010, 9:02 PM
CTrainDude CTrainDude is offline
Registered User
 
Join Date: Mar 2007
Posts: 517
Quote:
Originally Posted by fusili View Post
From what I heard, the NW line was delayed because the City thought they could get federal funding for it for the Olympics and therefore built the NE first. Kind of a sneaky move, but it makes sense. If the NW line was complete before the Olympic bid was won, the feds would not fund the NE line because it wouldn't have any benefit for the Olympics. Don't remember who I heard it from though.
I always thought that the NW was going to be built first, but the NIMBYs in Sunnyside convinced the City to do the NE first - hoping the people in other areas who wanted the line would put pressure on the people in Sunnyside when they saw the City was willing to move on.
     
     
  #289  
Old Posted Mar 30, 2010, 2:53 PM
You Need A Thneed's Avatar
You Need A Thneed You Need A Thneed is offline
Construction Enthusiast
 
Join Date: Feb 2007
Location: Castleridge, NE Calgary
Posts: 5,892
Whitehorn Station Upgrade link.

From calgarytransit.com.

I would stop in myself, but I'm busy wednesday evenings. Is anyone going that can collect information/brochures, and post it here?
     
     
  #290  
Old Posted Mar 31, 2010, 5:33 PM
You Need A Thneed's Avatar
You Need A Thneed You Need A Thneed is offline
Construction Enthusiast
 
Join Date: Feb 2007
Location: Castleridge, NE Calgary
Posts: 5,892
Quote:
Originally Posted by You Need A Thneed View Post
Whitehorn Station Upgrade link.

From calgarytransit.com.

I would stop in myself, but I'm busy wednesday evenings. Is anyone going that can collect information/brochures, and post it here?
Anyone going? The presentation is from 7- 7:30.
     
     
  #291  
Old Posted Mar 31, 2010, 6:25 PM
faxri faxri is offline
Registered User
 
Join Date: Dec 2005
Location: Calgary
Posts: 41
What is the current timeline for the south stations to be changed to 4 car lengths?
     
     
  #292  
Old Posted Mar 31, 2010, 6:42 PM
MalcolmTucker MalcolmTucker is offline
Registered User
 
Join Date: May 2007
Posts: 11,625
It is a stimulus project no? If so, it has to be done 1 year from today. (or at least all the money has to be out the door)
     
     
  #293  
Old Posted Mar 31, 2010, 6:47 PM
frinkprof's Avatar
frinkprof frinkprof is offline
Registered User
 
Join Date: Sep 2006
Location: The Gary
Posts: 4,865
Well the South and Northwest lines are scheduled to be done by 2014.
     
     
  #294  
Old Posted Mar 31, 2010, 7:34 PM
mersar's Avatar
mersar mersar is offline
Registered User
 
Join Date: May 2006
Location: Calgary, AB
Posts: 10,083
Quote:
Originally Posted by Sir.Humphrey.Appleby View Post
It is a stimulus project no? If so, it has to be done 1 year from today. (or at least all the money has to be out the door)
Part of it is. It was a $90M/$90M/$90M split between the 3 levels of gov't that funded the whole CT 'package'. So in my mind its possible they used the federal part for stuff underway already (SE BRT, 7th ave upgrades, GPS system, etc) while the rest will be used for later parts (11th street station, 4 car expansions, traction power upgrades, etc)
__________________

Live or work in the Beltline? Check out the Official Beltline web site here
     
     
  #295  
Old Posted Mar 31, 2010, 7:36 PM
faxri faxri is offline
Registered User
 
Join Date: Dec 2005
Location: Calgary
Posts: 41
Quote:
Originally Posted by frinkprof View Post
Well the South and Northwest lines are scheduled to be done by 2014.

Maybe they should just start on 5 car platforms
     
     
  #296  
Old Posted Mar 31, 2010, 7:39 PM
frinkprof's Avatar
frinkprof frinkprof is offline
Registered User
 
Join Date: Sep 2006
Location: The Gary
Posts: 4,865
Quote:
Originally Posted by mersar View Post
Part of it is. It was a $90M/$90M/$90M split between the 3 levels of gov't that funded the whole CT 'package'. So in my mind its possible they used the federal part for stuff underway already (SE BRT, 7th ave upgrades, GPS system, etc) while the rest will be used for later parts (11th street station, 4 car expansions, traction power upgrades, etc)
Global Positioning System system?
     
     
  #297  
Old Posted Mar 31, 2010, 7:54 PM
freeweed's Avatar
freeweed freeweed is offline
Home of Hyperchange
 
Join Date: Sep 2006
Location: Dynamic City, Alberta
Posts: 17,568
Quote:
Originally Posted by frinkprof View Post
Global Positioning System system?
Paid for by funds withdrawn from an ATM machine, using my PIN number.
     
     
  #298  
Old Posted Mar 31, 2010, 7:58 PM
frinkprof's Avatar
frinkprof frinkprof is offline
Registered User
 
Join Date: Sep 2006
Location: The Gary
Posts: 4,865
^And brought to you by the Department of Redundancy Department.
     
     
  #299  
Old Posted Mar 31, 2010, 8:32 PM
MalcolmTucker MalcolmTucker is offline
Registered User
 
Join Date: May 2007
Posts: 11,625
Quote:
Originally Posted by mersar View Post
Part of it is. It was a $90M/$90M/$90M split between the 3 levels of gov't that funded the whole CT 'package'. So in my mind its possible they used the federal part for stuff underway already (SE BRT, 7th ave upgrades, GPS system, etc) while the rest will be used for later parts (11th street station, 4 car expansions, traction power upgrades, etc)
I believe the program was designed to make sure the matching funds were spent by the end of next fiscal year aswell, or else we would have never got to 2% gdp. This was the reason they didn't allow stimulus funding for the Toronto streetcars.
     
     
  #300  
Old Posted Mar 31, 2010, 10:05 PM
lubicon's Avatar
lubicon lubicon is offline
Suburban dweller
 
Join Date: Jun 2003
Location: Calgary - our road planners are as bad as yours Edmonton
Posts: 5,047
Quote:
Originally Posted by faxri View Post
Maybe they should just start on 5 car platforms
Which is what Edmonton is building their new platforms to accomodate.
__________________
Two things are infinite: the universe and human stupidity; and I'm not sure about the the universe.

Albert Einstein
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Calgary > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 7:48 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.