Quote:
Originally Posted by satishreddy
UBC - 12000-15000 per day
Sasamat - 4000-6000 per day
Alma - 4000-6000 per day
MacDonald - 4000-6000 per day
Granville - 6000-8000 per day
Oak - 6000-8000 per day
Cambie 12000-15000 per day
Main 8000-10000 per day
There may be one more station between Main and Commercial/Broadway.
Broadway/Commercial 6000-8000 boarding to go west (not including people already on the train)
|
I think this number is a bit low, as your number only gives a ridership of 62000-83000 riders a day.
UBC - Using the 2008 data, if the SkyTrain take all of #44, #84, and #99 riders, and half of the riders on #4, #9, #17, #25, #480, this gives daily boarding of 15,500. If the ridership in UBC keeps with the pace of annual 3% growth in ridership, that gives a ridership of 22,100 by 2020, without taking into effect of the new rail system.
Sasmat, Alma, Macdonald - Using the 99 B-Line 2007 boarding and load data, assuming everyone who disembark at the station will board the train again in the return trip, annual transit ridership increase of 3%, and the increase of ridership of 80%, include conversion from local bus routes (as experienced from Canada Line):
Sasmat - 6800
Alma - 5800
Macdonald - 10,600
Granville - Assume 1/3 of the boarding of 99 B-Line come from 98 B-Line transfer, then the boarding would be 10,800
Oak - Using the data for Willow - 12,900
Cambie - Move the 1/3 transfer here, then add 50% for additional ridership from Canada Line and 25% of the ridership of #44 and #480 - 17,000
Main - Using the same method, 11,600
Commerical-Broadway - Assume the boarding on UBC line equals to the half of the rider alight the Expo Line who did not transfer to Millennium Line east, multiple by the same factor used above - 22,700
Total: 120,300, plus an increase of 3000 riders for VCC/Clark, plus some new riders from Finning and Arbutus.