City sketches LRT procurement timeline
By Peter Kovessy, Ottawa Business Journal Staff
Wed, Oct 14, 2009 4:00 PM EST
http://www.ottawabusinessjournal.com/295650365586026.php
A city official says the municipality will begin qualifying construction consortiums in mid-2010 to build the first phase of Ottawa's light-rail line, including the downtown tunnel that some are calling the biggest construction project in the city's history.
The request for qualifications process is expected to take eight months to a year and will be followed by a request for proposals being issued to qualified consortiums once preliminary design work is completed, said senior city project manager Dennis Gratton, adding actual construction should begin in 2012 or 2013.
A report must still go before committee and council outlining the procurement process, but city staff have already met with officials at Infrastructure Ontario, an arm's length provincial Crown corporation that uses private financing to renew and build public assets.
Speaking at the inaugural National Capital Heavy Construction Trade Show Wednesday, Mr. Gratton said the discussions have included the prospect of Infrastructure Ontario leading the project. The degree of private-sector involvement has also been debated, including the potential of having a private company operate or maintain the system, using an increasingly common public-private partnership model such as design-build-finance-maintain or design-build-finance-operate.
While it has not been definitively decided, Mr. Gratton said he believes government officials will award one large contract to a single consortium, rather than award several smaller contract packages. This was the route taken with the original north-south rail line, which would have been built by a consortium led by Siemens Canada Ltd., PCL Constructors Canada Inc. and Dufferin Construction Co.
This means that smaller companies must find the large firms that will be bidding on the project and align themselves with a bigger team. One local company with relevant niche expertise is Intera Engineering Ltd., which specializes in bedrock hydrogeology engineering consulting services.
"We need to find out who need to talk to, to make sure we are not forgotten," said Intera senior engineer Anthony West.
Ahead of the actual construction contract, there are several light-rail-related business opportunities o the horizon, particularly for Ottawa landowners.
The city has shortlisted approximately 10 candidate properties for the maintenance and storage facility. Staff will make a recommendation to council in December to purchase a particular property, which must be about 30 acres and be close to the rail line, said Mr. Gratton.
Additionally,
the city issued a request for information earlier this year for downtown "mining" sites that will be used as staging areas, as well as to provide ventilation, emergency access and allow equipment to be transported underground.
While Mr. Gratton said in an interview that the city has received a "very good response" to the request for information, he said the city has not shortlisted any excavation sites.
The first phase of the city's light rail proposal calls for a 12.5 kilometre line, running from Tunney's Pasture in the west to Blair station in the east. It includes a 3.2-kilometre downtown tunnel, running from just east of Booth Street to the University of Ottawa campus, and 13 stations.