Quote:
Originally Posted by Mininari
The closure of the King Edward underpass for construction of the new overpass makes a STRONG case to have the 4-lane bridge in place over the Brunette River as soon as possible on the United-Braid connection.
I guess its virtually impossible to maintain the current underpass while building an overpass overhead. They probably want to demolish the underpass and lower the highway FIRST, so they don't have to build the new overpass extra high.
|
That's correct. They were originally going with the curved route so they didn't have to demolish the overpass, but they will have a full close for 12 weeks for the work that can't be done while keeping the underpass open.
They will temporarily open up Taft Ave for easier access to WestBound Freeway travelers, which goes under the #1 at start of the Port Mann bridge, though. They're doing it in phases, but I hope they have a plan to fix the West end of UNited Blvd properly, instead of band-aiding it.