Quote:
Originally Posted by waterloowarrior
http://ottawa.ca/city_hall/rapid_transit/index_en.html
Getting it right - investing in the vision
Ottawa’s Transportation Master Plan contains a vision for transit to be developed by 2031. In the first phase, the City of Ottawa will invest in 40 km of new light rail transit (LRT) and vehicles to service these lines, as well as bus rapid transit (BRT) technology and additional bus lanes. This package—to be built in three stages—totals approximately $3.2 billion, and will be constructed as funding becomes available over the coming years, with early investment selected to address immediate needs and maximize return on investment.
The City is looking to senior levels of government to support this investment through Building Canada and successor funding programs.
Projects within Stage 1 include:
Transit Tunnel and LRT
The construction of the tunnel and LRT from Blair Station to Tunney’s Pasture, the cornerstone of the City’s transit plan, involves digging a tunnel from the University of Ottawa to Booth Street and converting 12 km of BRT to LRT in the east end. The City will work closely with the NCC to design stations that showcase Ottawa’s status as a capital city. It is estimated that this part of the project will employ some 7,000 people, directly or indirectly, over a two-year period, with a cost of $1.4 billion. In addition, a bridge over the Rideau River and Lees Avenue will be built to provide continuous Transitway service from the southeast to downtown, at an estimated cost of $45 million.
Expansion of Current Transitway
The Transitway will be expanded by adding a 15-km BRT system in east, west and south Ottawa. This will include: - The Cumberland Transitway from Blair Station to Navan Road (estimated cost: $49 million)
- The West Transitway from Bayshore Station to Moodie Dr., to serve residents of Kanata, Stittsville and Bayshore (estimated cost: $42 million)
|
This is getting pricey... last year it was priced at $39M for the entire run to Terry Fox (including about $20M of bridgework at March Rd but using the bus lanes on the 417 currently under construction):
W1 BRT BAYSHORE TO TERRY FOX: $39M
Quote:
- The Southwest Transitway from Fallowfield Park & Ride/VIA Station to Barrhaven Town Centre (estimated cost: $52 million)
|
This project is already funded under 2008 budget authority. It shouldn't even be here. And it costs $79M according the 2008 budget authority, so there's a ~$27M discrepancy here. Anyone got a pet transit project for $27M they'd like built?
Quote:
Strandherd-Armstrong Bridge, Approaches and Associated Work
One of the City’s most important network projects, this six-lane bridge crossing the Rideau River, with lanes dedicated for public transit, will link Prince of Wales Drive and Earl Armstrong Road. This project has an estimated cost of $102 million, which includes building the bridge, the widening of Earl Armstrong Road, a new transit station with a Park & Ride facility at Woodroffe Avenue and Strandherd Drive, as well as transit priority lanes from the new station along Woodroffe Avenue to the Fallowfield Park & Ride Station.
Baseline Rd. to Norice St. Rapid Transit
This new BRT/LRT major transfer station will integrate the Algonquin College expansion and the Centrepointe Town Centre future developments. This project will be a catalyst for the overall development of this important transit node. The project has an estimated cost of $207 million.
|
How is it we allowed Algonquin College to take an offer of free land and an expensive at-grade station ($20M) and turn it into an offer of free land and a very expensive tunnelized station?
Baseline Station is starting to give the DOTT a run for its money (literally). To put this in context, the estimated cost last year of running LRT on the surface downtown was $185M, so, based on last year's cost for Baseline Station ($20M), we could get LRT on the surface downtown AND a decent station at Baseline AND not affect the downtown tunnel at all for the cost of this grass-covered buried concrete monument.
What price, Algonquin College?
Quote:
Stage 2: Conversion of Transitway to Light Rail- Bayview Station to South Keys Station (estimated cost: $360 million)
- Tunney’s Pasture to Baseline Station (estimated cost: $542 million)
|
About a year ago, the costs for these were:
http://www.ottawa.ca/calendar/ottawa/cit...ntown%20Transit%20Final%2014%20April.pdf
C1 LRT GREENBORO TO BAYVIEW: $227M
C5 LRT BAYVIEW TO LINCOLN: $125M
C6 LRT LINCOLN TO BASELINE*: $110M
*including Baseline Station, then valued at $20M now at over $200M, above.
My guess is that they're dumping the vehicle requirements in at the same time... of course the busway projects listed here don't include buses.
Quote:
Stage 3: Expansion of Transitway and Light Rail- LRT expansion – South Keys to Riverside South Town Centre (estimated cost: $314 million)
- West Transitway extension – Eagleson Rd. to Terry Fox Dr. (estimated cost: $41 million)
|
Last year this cost $39M including the bit from Bayshore to Moodie (see above). Basically, the West Transitway from Bayshore to Terry Fox has doubled in cost.
Quote:
- West Transitway extension – Terry Fox Dr. to Scotiabank Place (estimated cost: $47 million)
|
Last year's cost:
W2 BRT TERRY FOX TO ARENA: $42M
Quote:
- Cumberland Transitway extension – Navan to Millennium (estimated cost: $72 million)
[re-copied from above:]
- The Cumberland Transitway from Blair Station to Navan Road (estimated cost: $49 million)
|
Last year's costs:
E3 BRT INNES TO MILLENIUM: $104M
E2 BRT BLAIR TO INNES: $24M
-> $128M then, $121M now
So there you have it: in the space of a year cost estimate changes up and down by margins small and enormous.