  #1081  
Old Posted Jan 30, 2009, 5:26 PM
twoNeurons twoNeurons is offline
 
Join Date: Aug 2002
Posts: 6,127
Quote:
Originally Posted by WarrenC12 View Post
A "city" the size of Port Moody is damn lucky to be getting any rapid transit.

What about getting a P3 partner in this climate? Is the province going to be the lender? Hopefully it doesn't take long to get "shovels in the ground".
Not to mention Commuter Rail to boot.
     
     
  #1082  
Old Posted Jan 30, 2009, 5:35 PM
djmk's Avatar
djmk djmk is offline
 
Join Date: Sep 2008
Posts: 1,825
Quote:
Originally Posted by WarrenC12 View Post
A "city" the size of Port Moody is damn lucky to be getting any rapid transit.
its because port moody is in between burnaby and coquitlam. just a geographical quirk of metro vancouvers 21 municipalities
     
     
  #1083  
Old Posted Jan 30, 2009, 6:48 PM
officedweller officedweller is offline
 
Join Date: Jul 2001
Posts: 41,816
The report that nname posted from 2001 shows that the Option B or B+ portals are "high risk" due to water-saturated poor soils (cost $21-30M) while the elevated section over Barnet is "low risk" with a cost of $8M.
http://www.translink.bc.ca/files/board_f...03-16_3-2_PtMdyCoq-PtMdyPortalOption.pdf

In terms of the transit riders' experience, having the tunnel portal in the hillside and emerging onto an elevated structure would provide amazing views - like the M-Line in New Westminster.

I think that having an elevated guideway adjacent to low to midrise housing is fine. There's a lot of housing like that along the Expo Line in Burnaby. As for a "Yaletown" character - that's just suburban real estate developers and marketers trying to cash in. There are lots of projects in Surrey touted as having a Yaletown feel - but end up looking like Fairview. Collingwood Village is successful and it is adjacent to an elevated segment.
     
     
  #1084  
Old Posted Jan 30, 2009, 6:56 PM
Metro-One's Avatar
Metro-One Metro-One is offline
 
Join Date: Sep 2008
Posts: 18,036
Doesn't Port Moody already have a "Yaletown" like area along the eastern shore of Burrard Inlet? How silly that they are going to complain about such a short elevated structure over a highway, for goodness sakes it will probably be similar to a large pedestrian overpass! I think if they really want the lower entrance that much then the city should pay the difference in costs compared to the higher tunnel entrance.
     
     
  #1085  
Old Posted Jan 30, 2009, 7:22 PM
officedweller officedweller is offline
 
Join Date: Jul 2001
Posts: 41,816
Yes it does - it's called Newport Village. Plus there's the other project across the street - Suter Brook?

Here's the aerial of the Andres lands from Global Air Photos (2004 & 2005)
Note that an elevated guideway would be high level when crossing Barnet Highway and appear even higher still on the Andres lands because the Andres lands are at a lower elevation.
Essentially, what you would see is like the Expo guideway as it transitions from Grandview Hwy North over Clark Drive and over the escarpment to the False Creek Flats.
That said, I still think that you can build condos in the area (and the CP tracks aren't moving).






Last edited by officedweller; Jan 30, 2009 at 7:51 PM.
     
     
  #1086  
Old Posted Jan 30, 2009, 7:48 PM
Mininari Mininari is offline
 
Join Date: Jul 2004
Posts: 2,447
Deleted: Posted same comments as Officedweller
     
     
  #1087  
Old Posted Jan 30, 2009, 10:32 PM
deasine deasine is offline
 
Join Date: Mar 2007
Posts: 5,747
Note: Post #1047, #1048, #1052, #1054-#1058, #1060, #1072, #1074-#1079, #1083, #1084 have been moved to the Intercity Transport Thread
     
     
  #1088  
Old Posted Feb 7, 2009, 5:38 AM
mr.x's Avatar
mr.x mr.x is offline
 
Join Date: Dec 2003
Posts: 12,805
Is there going to be an announcement/unveiling for the Evergreen Line anytime soon?

Anything dramatic like the recent unveiling + breaking ground of the new Port Mann? :p
     
     
  #1089  
Old Posted Feb 7, 2009, 7:33 AM
Whalleyboy's Avatar
Whalleyboy Whalleyboy is offline
 
Join Date: Jul 2008
Posts: 2,014
i bet its gonna be coming soon campbell just needs to finish up with getting things done in surrey=P
     
     
  #1090  
Old Posted Feb 7, 2009, 10:39 PM
GeeCee's Avatar
GeeCee GeeCee is offline
 
Join Date: Jan 2009
Posts: 2,816
I believe Falcon said in one of the tri-city newspapers that there would be an announcement 'soon'.
     
     
  #1091  
Old Posted Feb 9, 2009, 4:34 AM
d'ann d'ann is offline
 
Join Date: Sep 2008
Posts: 20
Bid info for evergreen line from Daily Commercial news

Wish I had a $1000 for a subscription as these docs wold make for an interesting read I think

http://dailycommercialnews.com/cgi-bin/t...d4b090&projectid=9053210&region=national

LRT SYSTEM, TUNNEL Proj: 9053210-5
Coquitlam, Greater Vancouver RD BC CONTEMPLATED
Evergreen Line - Segment 2.4, N of Morrison Ave to W of Barnett Hwy, V3J
$127,000,000 est
Start: 2010 Complete: 2014
Note: Funding has been secured from TransLink and the Provincial Gov't, but a final funding approval from the Federal Gov't is anticipated shortly. This project will be spearheaded by the Ministry of Transportation. An Evergreen Project Office will be opening shortly in Coquitlam. Further update over Spring 2009. See the other related segments to this project under project numbers: 9053203, 9053204, 9053206, 9053208, 7247183, 9053211 - 9053225.
Website: www.th.gov.bc.ca/evergreen_line. Total construction budget of Line is approx $1.4 billion. CH2M Hill is the Owner's Engineer.
Project: cast-in-place concrete foundation, 02230; site clearing, 02240; site preparation, 02410; tunnel excavation, 03210; reinforcing steel, 10530; canopies, light rail transit track way tunnel from Morrison Ave to the corner of the Barnett Hwy; this will be an ALRT (advanced light rapid transit) system.
     
     
  #1092  
Old Posted Feb 9, 2009, 5:39 AM
Spork's Avatar
Spork Spork is offline
 
Join Date: Sep 2008
Posts: 1,784
Quote:
Originally Posted by d'ann View Post
Wish I had a $1000 for a subscription as these docs wold make for an interesting read I think

http://dailycommercialnews.com/cgi-bin/t...d4b090&projectid=9053210&region=national

LRT SYSTEM, TUNNEL Proj: 9053210-5
Coquitlam, Greater Vancouver RD BC CONTEMPLATED
Evergreen Line - Segment 2.4, N of Morrison Ave to W of Barnett Hwy, V3J
$127,000,000 est
Start: 2010 Complete: 2014
Note: Funding has been secured from TransLink and the Provincial Gov't, but a final funding approval from the Federal Gov't is anticipated shortly. This project will be spearheaded by the Ministry of Transportation. An Evergreen Project Office will be opening shortly in Coquitlam. Further update over Spring 2009. See the other related segments to this project under project numbers: 9053203, 9053204, 9053206, 9053208, 7247183, 9053211 - 9053225.
Website: www.th.gov.bc.ca/evergreen_line. Total construction budget of Line is approx $1.4 billion. CH2M Hill is the Owner's Engineer.
Project: cast-in-place concrete foundation, 02230; site clearing, 02240; site preparation, 02410; tunnel excavation, 03210; reinforcing steel, 10530; canopies, light rail transit track way tunnel from Morrison Ave to the corner of the Barnett Hwy; this will be an ALRT (advanced light rapid transit) system.
$1000? It just sent it to me via email...

Quote:
Owner Ministry of Transportation, 4C, 940 Blanshard St, PO Box 9850 Stn Prov Govt, Victoria BC V8W 9T5, Phone: 250-387-1411 Fax: 250-356-8143; Dave Crebo

Land surveyor McElhanney Consulting Services, 780 Beatty St, Vancouver BC V6B 2M1, Phone: 604-683-8521 Fax: 604-683-4350

Civil cons eng MMM Group Limited, 1455 W Georgia St Ste 600, Vancouver BC V6G 2T3, Phone: 604-685-9381 Fax: 604-683-8655

Consultant CH2M Hill Canada Ltd, 2100, 4720 Kingsway, Twr II, Burnaby BC V5H 4N2, Phone: 604-684-3282 Fax: 604-684-3292

Geotechnical cons Golder Associates Ltd, Ste 500, 4260 Still Creek Dr, Burnaby BC V5C 6C6, Phone: 604-296-4200 Fax: 604-298-5253
Is that what you wanted?
     
     
  #1093  
Old Posted Feb 9, 2009, 6:06 AM
d'ann d'ann is offline
 
Join Date: Sep 2008
Posts: 20
bid docs

no I want what ever is known on current routing and station locations. After all these years too many details have not been released
     
     
  #1094  
Old Posted Feb 9, 2009, 6:10 AM
Spork's Avatar
Spork Spork is offline
 
Join Date: Sep 2008
Posts: 1,784
What would you subscribe if you wanted these? I may be able to get the data from some online databases that I have access to.
     
     
  #1095  
Old Posted Feb 9, 2009, 10:22 AM
GeeCee's Avatar
GeeCee GeeCee is offline
 
Join Date: Jan 2009
Posts: 2,816
Ah, I kind of figured that would be for the Evergreen line..

A semi-temporary building is going up at the Coquitlam Center park and ride. I guess that is for the Evergreen office. It's almost done from the looks of it. I imagine it'll be set to open for when funding is finalized.
     
     
  #1096  
Old Posted Feb 9, 2009, 6:37 PM
Mininari Mininari is offline
 
Join Date: Jul 2004
Posts: 2,447
Oh, how progess is asymptotic to actual contruction... we just keep getting closer and closer... and then finally... finally....
     
     
  #1097  
Old Posted Feb 9, 2009, 8:24 PM
officedweller officedweller is offline
 
Join Date: Jul 2001
Posts: 41,816
Quote:
Originally Posted by d'ann View Post
no I want what ever is known on current routing and station locations. After all these years too many details have not been released
Since it has gone back to being SkyTrain - check out these 4 docs from 2002 that were posted by nname - that pretty much sums up the options. I think the future Cameron Station has been deleted (feasibility would probably depend on if it is built as a side-of-the-road guideway - definitely deleted as a future station if it is a median guideway).

Quote:
Originally Posted by nname View Post
There are already lots of info if you dig into the archive.. something like this, this, this, and this. I wonder how much of these can be re-used...
     
     
  #1098  
Old Posted Feb 9, 2009, 8:37 PM
deasine deasine is offline
 
Join Date: Mar 2007
Posts: 5,747
I think the west alignment option should be a given. We can see the success of that already with the No. 3 Rd. But if the are going with the center median, please do the the enhanced median design.
     
     
  #1099  
Old Posted Feb 10, 2009, 4:55 AM
Jared's Avatar
Jared Jared is offline
 
Join Date: Oct 2001
Posts: 4,051
Quote:
Originally Posted by d'ann View Post
no I want what ever is known on current routing and station locations. After all these years too many details have not been released
Well, it's the NW route, the alignment can be found on the Translink website.

The PTV study done for Translink modeled stations at Lougheed, Burquitlam, Queens, Port Moody Station, Ioco, Coquitlam Station, Lincoln and Guildford.
     
     
  #1100  
Old Posted Feb 10, 2009, 9:11 PM
officedweller officedweller is offline
 
Join Date: Jul 2001
Posts: 41,816
Quote:
Originally Posted by deasine View Post
I think the west alignment option should be a given. We can see the success of that already with the No. 3 Rd. But if the are going with the center median, please do the the enhanced median design.
But for the PMC Line they were going to go down the middle of North Road since its the dividing line between Burnaby & Coquitlam and neither city's politicians wanted to be saddled with the impacts more than the other.

The key to a future station would be to have the station site on the side of the road - either west side or east side. The guideway could run up the west side along mall property to the station site (at the corner of the mall property & the new Silouette condo), then transition to the median after the station site if the new Silouette condo project blocks the west allignment ROW. Ideally the guideway should stay on the west side until it turns into Clark Road where it can enter the median and Burquitlam station could be a trench station in the median at the portal.

Hopefully someone will explain the difference in the impacts and feasibility of options between the west allignment and the median allignment to the politicians.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 12:30 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.