Quote:
Originally Posted by Mininari
Looks pretty "shovel ready" to me.
But then again, it would sure "stimulate the local economy" to just redesign the whole darn thing again. Why not?
|
Well, detailed design only begins once the contract has been awarded. In terms of preliminary design, I thinm most of those reports have be dusted off, and simply updated where needed. For example, the run-the-guideway-on-the-west-side-of-North-Road idea may no longer be an option, due to construction of several highrises there since that report was done.
Also, there will hopefully be another train yard thrown into the mix somewhere, which I dont think was in the original plan (the Edmonds yard is going to run out of space eventually). Also, there are two more stations this time around, a third Port Moody station, and a total of 3 stations along the Pinetree way corridor (compared to 2 before hand, one at the WCE, and one at either Lincoln or Guildford).