Quote:
Originally Posted by ravman
ahhaha you would THINK so... but the Gordo and company are going to force a P3 who is then going to turn around and cut corners left right and center.... you saw how they botched the Canada line... single tracking, cut/cover 40m platforms etc etc.... I already see SNC Lavalin outside the gordo's office trying to win the contract and so they can botch yet another rapid transit.
The NDP, i believe, in their policies supports a ALRT to Douglas College and with a change in government, they are going to actually build the thing. Everyone wants this done sooner rather than later and Because Everyone Matters, the NDP is actually going to build a line out beyond Coq Station.
Sorry i know the truth hurts, but it was the NDP that built the Millennium Line in a manner that was compatible with the existing system and the Liberals built the Canada line using a different technology, which meant increased cost for a OMC and different trains. The logical thing was to connect it to Waterfront station and have it more convenient for "Everyone". It was the NDP who built switches and a third track to accomodate a future extension beyond Coq Station!
|
A couple of points:
- The number of scope cuts from the Canada Line was regrettable, but it was not InTransitBC's uniliateral decision to change scope, it all had to be approved by RAVCO. Blaming InTransitBC is like blaming a car dealer for not giving you a Ferrari after you agreed on (and paid for) a Honda Civic.
- Am I to understand you believe the province should have put an extra billion dollars into the Canada Line (to get rid of the P3 component, and to pay for all the extra scope)? Please clarify. Also, isn't the NDP critical of pumping in extra dollars to complete a project instead of cutting scope (see Convention Centre).
- The 40m platforms aren't really a big deal, the real issue is the lower maximum capacity (of which the platform lengths are a component).
- Another OMC would be needed anyways, the Edmond's yard wont be able to hold all the extra trains being thrown at it. This is the reason why there will likely be another OMC in Coquitlam.
- The Canada Line is connected at Waterfront station, unless you mean continuing the same tracks. They're pointing the wrong way. There was a study done in 2003 which proposed this, but the line took a different (and IMO inferior) route that connected to Stadium station.
- You claim the NDP is planning to build a line out past Coquitlam Station. Are you suggesting the Evergreen Line as planned will not go all the way to Douglas? Or are you suggestion the NDP wants to build something east of Coquitlam Station? Do you have any evidence for these plans? And I mean something a bit more concrete than the transport critic mentioning "I think it might be a good idea" in a local newspaper.
Lastly, the funniest thing about your entire rant is that you seem to have missed the biggest blunder the Liberals made WRT the Evergreen Line: Cancelling it in the first place. If they hadn't axed the orignal plan, it could have been built much cheaper and much sooner (I think the original year 2000 cost estimate was $700 million. I belive this only went to Lincoln though, not Douglas). How on earth did you miss this?