Tower 4 hasn't really been delayed, but you know how the media loves those "WTC delay" stories...
http://www.reuters.com/article/marketsNews/idUSN1245855120081212
World Trade Center rebuilding faces new delays
Fri Dec 12, 2008
By Joan Gralla
NEW YORK, Dec 12 (Reuters) - The New York-New Jersey Port Authority will miss another deadline for rebuilding the World Trade Center and must resume paying developer Larry Silverstein $300,000 a day in penalties until it finishes preparing his sites, both parties said on Friday.
Silverstein is building three office towers and the Port Authority is building the 1,776-foot (541-meter) Freedom Tower, which will not be delayed, an agency spokeswoman said.
"The Freedom Tower is on track and is rising," she said. The Freedom Tower, designed to symbolize New York's revival after the Sept. 11 attacks, should open in 2013, four years later than originally planned.
Silverstein's towers, which will encircle the memorial, may now be delayed further though the agency stressed it was cooperating, instead of clashing, with the developer.
"We're still determining any impact, but we're working together to minimize any potential delays," the Port Authority spokeswoman said.
The Port Authority also said it will miss a Dec. 31 deadline for additional site preparation, including tracts of land for two of Silverstein's towers.
These are Tower 2, designed by architect Norman Foster, who topped it with four diamond-shaped towers, and Tower 3, whose facade designed by Richard Rogers features diagonal supports.
After missing a July deadline, the Port Authority later said it had finished preparing some sites, but Silverstein contested the work and arbitrators ruled in his favor.
The ruling reinstated penalties that help offset the $215,000 a day in rent the developer pays the Port Authority.
Disputes about insurance, design, security and the memorial to the nearly 3,000 people who died when the World Trade Center was destroyed have added years to the rebuilding process.
Silverstein and the agency rewrote their contract in 2006, adding deadlines and penalties. The agency missed its first deadline in February and finished that work 48 days late.
In March, New York Gov. David Paterson inherited the project from two predecessors and chose a new overseer to clear logjams.
Arbitrators on Friday ruled the agency failed to finish the part of the anti-flooding support wall and failed to finish site work for Tower 4, which Japan's Fumihiko Maki designed with a metallic mesh to echo Manhattan's Chrysler building.
The agency's effort to speed the work by modifying supports for a subway that runs through the site caused the delay.
Arbitrators also ruled that the Tower 2 site was not ready because the state agency that runs the subway had not approved plans.
The Port Authority wants the U.S. government to extend a 2009 deadline for Liberty Bonds, tax-free debt approved to help fund the project. The credit crunch that has halted many New York City developments makes those bonds especially attractive.