This is the status of FasTracks EIS's that are complete or scheduled to be complete by the end of this year or the project's current schedule:
-
West Corridor LRT: completed the
Environmental Impact Statement in 2003 and began Final Design in November 2005. During Final Design, an
Environmental Assessment was prepared that addresses all environmental impacts due to changes from the original EIS document. It will be the first corridor to be completed in the FasTracks program, opening in early 2013.
-
Denver Union Station On October 17, 2008, the Federal Transit Administration (FTA) signed the
Denver Union Station (DUS) Record of Decision (ROD) which confirms that construction of the proposed arrangement of transit improvements can proceed. The ROD includes the light rail, passenger rail and regional bus facilities as well as associated site improvements.
-
Gold Line EMU: RTD is now hard at work completing the Final Environmental Impact Statement (FEIS), which is scheduled for release in early 2009.
The Gold Line Draft Environmental Impact Statement (DEIS) is complete.
-
East Corridor EMU: began the Environmental Impact Statement for this project in July 2003. The
Final Alternatives have been selected. The
Draft Environmental Impact Statement (DEIS) will be released in January 2009. The Final EIS will be released in July 2009. The Record of Decision will be released in October 2009.
-
US-36 BRT Corridor: The
Draft Environmental Impact Statement for US 36 began in 2003 and was completed in 2007. The
Final Environmental Impact Statement is scheduled to be
complete in 2009.
-
NW DMU Rail Corridor: will not meet minimum federal ridership estimates to qualify for Federal Funding and thus does not need to complete an EIS. Instead, an
Environmental Evaluation (EE) and a Finding Of No Significant Impact (FONSI) is due to be complete by January 2009. Final Design/ROW Acquisition is to be complete by late 2010.
-
North Metro DMU: will not meet minimum federal ridership estimates to qualify for Federal Funding and thus does not need to complete an EIS. Instead, an
Environmental Evaluation (EE) and a Finding Of No Significant Impact (FONSI) is due to be complete by January 2009. Final Design/ROW Acquisition is to be complete by late 2010.
-
I-225 LRT extension Project schedule has environmental planning completion by first quarter of 2011 and construction starting at that time.