Quote:
Originally Posted by WonderlandPark
Months ago, I got heat for saying that this will probably get delayed again and again, well, told you so. Look for Park 5th to cancel or delay indefinitely.
|
It seems like it was only a few months ago that I thought it was reasonable to assume that proj, originally announced to be under way in late 2007, wouldn't break ground til the revised date of 1st qtr of this yr. Then another revised date of last qtr of 2008, or right around now, sounded reasonable. But now the idea of that tower beginning to rise sometime even in 2009, even the
last day of 09, doesn't sound realistic. So it's becoming deja vu all over again.
The devlpr of park 5th proposed another large proj back in the 1980s, which also never saw the light of day. I hate to think that history is repeating itself. Even more so since the NE corner of 5th St & Olive has been one of the bigger deadzones in the hood, sapping even more life out of Pershing Sq.
But the situtation is getting so dicey throughout the country & world, that even if park 5th, or also the Grand Ave proj, broke ground right now, that in itself
wouldn't necessarily mean or guarantee anything.
At the Spire site, 400 N. Lake Shore, the grandly conceived tower is nothing more than a hole in the ground surrounded by a ring of caissons. Construction cranes are gone. It is unclear when, if ever, they will return. Developer Garrett Kelleher has spent at least $50 million on construction, according to project spokeswoman Kim Metcalfe. She cites that investment as evidence that work on the project will resume and that it will open in 2012, even though the skyscraper's star architect, Santiago Calatrava, recently filed a lien seeking more than $11.3 million in payment from Kelleher.
"When you've invested this much time, effort and tangible money in the project, it is not not going to happen," Metcalfe said.
Work also is frozen at 111 W. Wacker Drive, home to Chicago's other stalled supertall skyscraper, the Waterview Tower and Shangri-La Hotel. (To be considered "supertall," a skyscraper needs to be at least 1,000 feet high.) The firm that developed and designed Waterview, Chicago-based Teng, planned for it to reach an impressive 1,047 feet, a foot taller than New York's celebrated Chrysler Building. Instead, the project is stuck on the 26th floor, its exposed concrete frame looming over Wacker.
Teng announced in April that the Beijing Construction Engineering Group Co. Ltd. and its American subsidiary would arrange for more than $300 million in construction financing to finish the job. Yet construction remains on hold. Sean McMahon, a spokesman for Teng, did not return telephone calls.
There are other signs of a skyline on hold. Since July, there has been no construction on the 16-story Staybridge Suites hotel at 127 W. Huron St., where the developer is Duke Miglin, son of cosmetics entrepreneur Marilyn Miglin and the late developer Lee Miglin. Although the building's innovative structural frame is complete, the frame is not covered. And winter is coming, with its destructive snow and ice.
"You can't let building materials sit exposed that weren't intended to be exposed for a long time," said the building's architect, Joe Valerio of Chicago. Miglin did not respond when asked to discuss the project.