Since we're in such a state of flux (to put it as kindly as possible) I thought I'd do a quick status update of some of the bigger current and planned projects here in the rundown thread. Please add/correct/edit as needed.
Transbay Tower - Hines deal approved; awaiting final approval of height zoning changes; I'm just hoping Hines doesn't back out with this economy.
301 Mission - tower and midrise exteriors basically complete; interiors and grounds under construction
One Rincon Hill phase 1 - tower complete; townhomes and landscaping approaching completion
One Rincon Hill phase 2 - on hold
555 Mission - complete; finishing plaza and interior
535 Mission - on hold; excavation complete; piles driven
350 Mission - expected to start in 2009; I'm dubious
The Californian (375 Fremont) - Fifield is trying to sell their development entitlements; basically dead for now
45 Lansing - hard to tell, but I wouldn't be surprised if it officially goes on hold in the near future
Infinity - tower 1 and townhomes complete; tower 2 exterior complete; courtyard nearing completion
631 Folsom - facade largely complete, interior, ground level and landscaping in progress
340-350 Fremont - Peebles is trying to sell their development entitlements; basically dead for now
10th and Market - checked today and the site hasn't been touched; last we heard it was supposed to start in the Fall; has anyone heard anything new?
350 Bush - was supposed to be delivered in 2009; entitled through 2010; nothing is happening onsite; I think it's on hold/dead, but no official statement to that effect
One Hawthorne - under construction; pouring underground levels; rebar up to about street level
Trinity - under construction; I checked today and they're working on level 12