Geology causes change at Constellation. Not sure what is being flipped but
a slight delay in any case. This is common downtown as there are many underground voids, caves etc.
By GINA HANNAH
Times Business Writer
[email protected]
Large variations in bedrock force footprint of development to flip
A hotel planned for the Constellation development downtown will have to be redesigned because of the geology of the site.
Scott McLain, who's developing the mixed-use project off Clinton Avenue near South Memorial Parkway, said crews have discovered nearly 50-foot variations in the depth of the bedrock where the six-story SpringHill Suites was to be built. McLain said construction likely will be delayed for a couple of months.
"Everything will proceed as scheduled," McLain said Monday. "It's just that the footprint will be flipped."
The 153-room SpringHill is the first of two hotels slated for Constellation. The second, also expected to be a Marriott brand, will begin construction after the SpringHill is completed.
In addition, Yedla Management of Huntsville, which will develop and operate the hotels, plans to build a 3,500-square-foot meeting space connecting the hotels. Construction costs for the SpringHill and meeting space are estimated at $20 million.