The photos and report can be found here:
http://www.theaustonian.com/pics/2008-08-08_Austonian%20Report_44.pdf
And here are the details:
Work activities completed thru August 8, 2008:
• August starts our 11th month of construction activity
• Level 11 poured on August 2, 2008
• Level 12 vertical structural members 100% complete
• Level 12 decking and rebar 75% complete
• Level 12 deck to pour August 11, 2008
• Podium “Top-Out” Appreciation Luncheon held for the workers on August 2, 2008
• Man/material hoist extended to level 10 for operation starting August 15, 2008
• Masonry work 80% complete at all areas
• Steel stair towers in podium to be 100% complete by August 15, 2008
• MEP rough-in continues at podium and tower
• New subcontractors recently added to the team; painting, counter tops and millwork