Road construction updates from the Huntsville Planning Department, (from HSV Times article)
http://www.al.com/news/huntsvilletimes/kclines.ssf?/base/news/1217754911118160.xml&coll=1
The service road for the proposed Harris Hills commercial development at U.S. 72 and Moores Mill Road "is well ahead of schedule." The service road, which runs from High Mountain Road to Old Gurley Pike, is about 80 percent complete. The job was scheduled to be completed in February, but now is expected to be done this month.
The widening of Governors Drive to seven lanes between Monroe and Gallatin streets is expected to be completed this fall. Storm drainage work is under way with curb and gutter work to follow.
The update reports that city engineers said the actual Governors road work may be completed late in the summer followed by "off the roadway" work such as building sidewalks and installing utility poles to finish the project.
The widening of Oakwood Road from Old Monrovia Road to Research Park Boulevard is about 60 percent complete and is expected to be finished late this fall.
The pedestrian improvement project in Five Points is about 35 percent complete and is scheduled to finish in October.
Changing the Jeff Road intersection at Alabama 53, and widening Alabama 53 on both sides of the intersection, is about 35 percent complete but no completion date has been set.
The Memorial Parkway overpass and main lanes from Whitesburg Drive to Weatherly Road is about 20 percent complete and is expected to be finished in January 2010.
The Gillespie Road extension from Browns Ferry Road to Balch Road in Madison is about 20 percent complete. A completion date has not been determined.
Widening Winchester Road to five lanes from the Huntsville city limits near Valhalla Funeral Home past Moores Mill Road to Dominion Circle began in early July. Problems getting utilities such as telephone and television cable lines moved prevented construction from beginning sooner. The contractor has 300 working days to complete the project, which means it could continue through much of 2009.
Clinton Avenue closing
The west end of Clinton Avenue will close to through traffic for several months beginning Monday morning for a bridge replacement project at Broglan Branch.
Miller and Miller Inc., which was awarded a contract by the city for the work, will close the street at 7 a.m. Monday, said Mark Sealy, project manager for Miller and Miller.
The bridge replacement and related drainage improvements to Broglan Branch on each side of Clinton could take four or five months, he said.
A detour using Seminole Drive to travel between Clinton and Governors Drive will be marked, Sealy said.