Quote:
Originally Posted by NYC4Life
Towards the end of the year we should start seeing more cranes at the site and the first steel beams being erected on Towers 2, 3, and 4.
|
I don't think we're scheduled to see steel on those towers until next year...
(the dates have already been pushed back a few months from posted dates)
Tower 2
Foundation Construction.............. July - December 2008
Construction Drawings................. April 1, 2008
Superstructure to Ground Level..... January - July 2009
Structural Steel Erection.............. July 2009 - March 2011
Structural Concrete Tower Core & Slab.......... October 2009 - June 2011
Core and Shell Work.................... March 2010 - December 2012
Curtain Wall............................... April 2010 - March 2012
Tower 3
Foundation Construction.................. January - July 2008
Construction Drawings..................... April 1, 2008
Superstructure to Ground Level......... July 2008 - January 2009
Structural Steel Erection.................. January 2009 - September 2010
Structural Concrete Tower Core & Slab........... March 2009 - November 2010
Core and Shell Work........................ September 2009 - December 2011
Curtain Wall......................... November 2009 - March 2011
Tower 4
Foundation Construction........................ January - July 2008
Construction Drawings........................ April 1, 2008
Superstructure to Ground Level............ July 2008 - January 2009
Structural Steel Erection......................... January 2009 - September 2010
Structural Concrete Tower Core & Slab............ March 2009 - November 2010
Core and Shell Work.......................... September 2009 - December 2011
Curtain Wall................................ November 2009 - March 2011
The combined delays of Silverstein and the Port Authority have pushed these towers back to 2012...
Quote:
|
As of today, my company’s projects – Towers 2, 3 and 4 – are fully designed and on schedule. Construction of Towers 3 and 4 is underway, and all three buildings are slated for completion, as projected, by the end of 2012.
|