A nice little update from our friends at
www.webcor.com with mostly information that we know or have speculated about. Cool new pictures though:
FEBRUARY 2008
TOWER
Webcor & Millennium celebrated the “Topping Off” for the tower structure on Friday, February 8, preceded by a world class BBQ and a brass band. The final ceremonial concrete bucket with the traditional tree was hoisted to the top of the building to mark its structural completion. Although this may be the completion of one step, the actual finish won’t happen for a year.
The crane logistics has started in the middle of February with the “roof mounted” crane being placed on level 59. The “tower” crane will be gone before the end of the month and the “roof mounted” crane will “pick up” the load where the tower crane left off. The next step of this tedious procedure won’t occur until sometime this coming May.
The tower’s dress blues (the window wall) will have crept up to level 44 by the end of February. The building is expected to be fully glazed by the end of the May to early June.
The labor intensive interior work is marching up the building transforming a gray and sparse concrete space into elegant condominiums. As simple as sentence might describe it; there’s high amount of time and coordination required to successfully complete the interior finishes in a project of this magnitude. As of this writing, just in the “Tower” structure itself, the project is currently involving more than 20 Subcontractors and roughly 250 craft workers currently spanning the height of the building. The first milestone for this scope will be the “punch list” of the first finished floors.
MID-RISE
Webcor Concrete has been moving along like a steam locomotive by running a six day floor cycle! By the time we say hello to March, the level 9 deck will have been curing for a day or two. Don’t blink; the concrete will be topped out in the Mid-Rise very shortly.
The structural steel work will kick off with three big beams in the atrium area and later on a series freshly painted cantilevered beams will be hung over the remaining area of the atrium. After this scope of work has been completed there’s only two more major steel activities remaining for the mid-rise.
Good news! The storefront work has commenced and the Subcontractor will be busy during the month of February doing layout and setting up steel supports. We’ll keep you posted.