  #121  
Old Posted Jan 23, 2008, 2:42 AM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin<--->Birmingham<--->Atlanta
Posts: 55,832
I can't believe they'll need two tower cranes. Apparently they will as they're talking about it with that report, but man, the footprint of this tower is tiny.

Screenshots from that page:


Photo credit goes to: http://www.theaustonian.com/pics/2008-01-19_Austonian_Report_18.pdf


Photo credit goes to: http://www.theaustonian.com/pics/2008-01-19_Austonian_Report_18.pdf
__________________
My girlfriend has a poodle named Kevin.
     
     
  #122  
Old Posted Jan 23, 2008, 3:10 AM
Complex01's Avatar
Complex01 Complex01 is offline
Endless Moments...
 
Join Date: Aug 2006
Location: Texas...
Posts: 2,917
Oh very nice. Did not know the crane was up. Very kewl...

     
     
  #123  
Old Posted Jan 29, 2008, 2:23 AM
Blakesalot!'s Avatar
Blakesalot! Blakesalot! is offline
Registered User
 
Join Date: Aug 2006
Location: Austin, TX
Posts: 129
New Austonian Construction Report: http://www.theaustonian.com/pics/2008-01-28_Austonian_Report_19.pdf
(Includes a good number of photographs)


From the report:

Work activities completed through January 25, 2008:

• Mat slab excavation complete and material removed from site
• Mud slab poured at mat slab to facilitate reinforcing steel installation
• Rebar crew currently installing 2nd layer of steel for mat slab
• Slab pour to be completed on Saturday 2-2-08 or 2-9-08 contingent on weather
• Perimeter concrete wall footings 75% complete
• Wall forming of basement walls to begin next week
• Pier caps 80% complete
• Concrete foundation for tower crane #2 in progress
• Tower crane #2 structural base to be delivered and installed next week
• Sub grade preparations and compaction operations in progress for B-1 slab
• Waterproofing of below grade walls started on 1-20-08
• Utility work along Congress Avenue begins on 1-24-08
• Blockout forms for elevator shafts being constructed on site
• Compaction operations at sump pits in progress
• Coordination and preparations for under slab plumbing rough-in underway
• Painting of barricades along Congress Avenue in progress
• Lighting installed in Congress Avenue pedestrian tunnel
     
     
  #124  
Old Posted Jan 29, 2008, 3:55 AM
texboy texboy is offline
constructor extrodinaire!
 
Join Date: Nov 2004
Location: Denver, CO
Posts: 1,752
Tower Crane #2 Base has been installed btw... was on the site today.
     
     
  #125  
Old Posted Jan 29, 2008, 3:13 PM
priller's Avatar
priller priller is offline
Registered User
 
Join Date: Apr 2007
Posts: 1,979
Mat slab rebar getting put in place:





     
     
  #126  
Old Posted Jan 29, 2008, 3:16 PM
priller's Avatar
priller priller is offline
Registered User
 
Join Date: Apr 2007
Posts: 1,979
Quote:
Originally Posted by texboy View Post
Tower Crane #2 Base has been installed btw... was on the site today.
The second crane, will it be used mainly for the base floors? Kind of like the front crane at Altavida? Or will it be used for the tower portion also?
     
     
  #127  
Old Posted Feb 4, 2008, 8:35 PM
priller's Avatar
priller priller is offline
Registered User
 
Join Date: Apr 2007
Posts: 1,979
From Sunday, 2/3/08. You can see the mat slab was poured over the weekend. You can also just make out the second crane base in the very back.


Last edited by priller; Feb 5, 2008 at 4:07 PM.
     
     
  #128  
Old Posted Feb 5, 2008, 1:22 AM
texboy texboy is offline
constructor extrodinaire!
 
Join Date: Nov 2004
Location: Denver, CO
Posts: 1,752
Yea thats basically what it will be used for. Crane in the middle of the site is the one that will be jumped as the building goes vertical.
     
     
  #129  
Old Posted Feb 5, 2008, 3:59 PM
J.Dskyhigh's Avatar
J.Dskyhigh J.Dskyhigh is offline
Registered User
 
Join Date: Sep 2007
Location: san antonio
Posts: 98
Quote:
Originally Posted by priller View Post
From Sunday, 4/3/08. You can see the mat slab was poured over the weekend. You can also just make out the second crane base in the very back.

You do mean 2/3/08 right? Just getting it clear.
     
     
  #130  
Old Posted Feb 5, 2008, 4:07 PM
priller's Avatar
priller priller is offline
Registered User
 
Join Date: Apr 2007
Posts: 1,979
Oops, yes, thanks.
     
     
  #131  
Old Posted Feb 7, 2008, 2:19 AM
Blakesalot!'s Avatar
Blakesalot! Blakesalot! is offline
Registered User
 
Join Date: Aug 2006
Location: Austin, TX
Posts: 129
New Construction Report Posted:

http://www.theaustonian.com/pics/2008-02-04_AustonianReport_20.pdf

From the report:

• Mat slab concrete pour completed February 2, 2008 (+1900 cubic yards)
• Tower crane #2 foundation poured
• B-1 concrete column forming and pouring started February 1, 2008
• Bentonite waterproofing of below grade walls 50% complete
• Perimeter B-1 wall forming started January 30, 2008
• Pier cap forming continues
• Site utilities along Congress Avenue continue
     
     
  #132  
Old Posted Feb 7, 2008, 2:26 AM
Deepstar's Avatar
Deepstar Deepstar is offline
Registered User
 
Join Date: Mar 2007
Location: Canada
Posts: 6,291
Nice to see this one coming along.
     
     
  #133  
Old Posted Feb 7, 2008, 8:27 PM
priller's Avatar
priller priller is offline
Registered User
 
Join Date: Apr 2007
Posts: 1,979
What's amazing is that I went by today and the site already looks completely different from these report photos just a few days ago. They've got the slab covered with forms, columns are sprouting up everywhere, the basement wall forms are going up all around. I'm very impressed with how quickly things are moving now that most all the foundation work is done.
     
     
  #134  
Old Posted Feb 7, 2008, 9:01 PM
chex's Avatar
chex chex is offline
Registered User
 
Join Date: Aug 2006
Location: gdl/ldn/ny
Posts: 2,232
the hole doesnt seem that big to have an underground parking... does it exists on the plan?
     
     
  #135  
Old Posted Feb 7, 2008, 9:47 PM
priller's Avatar
priller priller is offline
Registered User
 
Join Date: Apr 2007
Posts: 1,979
I believe there's only 1 basement floor, mostly parking. The other parking levels are above the ground floor retail.
     
     
  #136  
Old Posted Feb 22, 2008, 5:29 AM
priller's Avatar
priller priller is offline
Registered User
 
Join Date: Apr 2007
Posts: 1,979
New Austonian construction update. The date says 2/16 but I think it was just recently posted.

http://www.theaustonian.com/pics/2008-02-16_Austonian%20Report_22.pdf

Work activities completed thru the week ending February 16, 2008:

• Elevator shear walls poured at level B-1
• Concrete walls for garage ramp at B-1 poured
• Gravel backfill for slab of garage ramp installed and compacted
• Cast iron under slab rough-in 75% complete
• PVC under slab drainage pipe 75% compete
• Electrical rough-in in progress
• Waterproofing of below grade walls continues
• Pouring of concrete walls at B-1 continues
• Pouring of wall footings at south wall to start February 18, 2008
• Tower crane #1 “initial jump” to take place February 17, 2008. 5 sections to be added to tower (+/- 100’)
• Next critical milestone: pouring B-1 slab on grade scheduled for February 26, 2008
     
     
  #137  
Old Posted Feb 24, 2008, 6:11 PM
ATXboom ATXboom is offline
Registered User
 
Join Date: May 2007
Posts: 1,832
http://www.austintowers.net/Austin_Downtown/index.html

New: Austonian Listings Added to AustinTowers.net
February 24, 2008 09:11 Filed in: Development Watch
The Austonian is one of the most luxurious and desirable downtown projects currently under development. With an unusually secretive sales process, details on pricing and sales have been hard to come by.

Over the last few weeks, many new details have become public as the project has begun to list a small number of unsold units on the Austin Multiple Listing Service (MLS). Starting today, we have added these listings to the AustinTowers Listings page. The new Austonian Listings can be found here.

The 4 listied units (as well as a fifth on the Gottesman Residential site) show a broad range of prices for units, with the highest prices rightfully reserved for the units on the highest floors. The prices for listed units range from $559,000 to $1,855,000 for units ranging from 1,221 to 3,129 square feet. What the units have in common is that they are in an exclusive building with super-high-end finish out, appliances, and building amenities.

One of the most interesting details to emerge is the variance in pricing on a per square foot basis from unit to unit. For the five listed units, price per square foot varies from $458 / Square Foot to a whopping $830 / Square Foot for Unit 41Q, a 2,235 square foot 2 bedroom unit on the 41st floor.

The following new renderings provide an interesting glimpse into the the planned Austonian interiors:
     
     
  #138  
Old Posted Feb 29, 2008, 3:02 PM
Xeelee's Avatar
Xeelee Xeelee is offline
Baryonic Lord
 
Join Date: Nov 2003
Location: Houston
Posts: 2,074
This looks really nice. I would like to see it in person.
     
     
  #139  
Old Posted Mar 1, 2008, 12:53 AM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin<--->Birmingham<--->Atlanta
Posts: 55,832
Photos from 2/24.



__________________
My girlfriend has a poodle named Kevin.
     
     
  #140  
Old Posted Mar 8, 2008, 2:13 PM
priller's Avatar
priller priller is offline
Registered User
 
Join Date: Apr 2007
Posts: 1,979
Getting ready for the second crane:



     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
 

Go Back   SkyscraperPage Forum > Discussion Forums > Buildings & Architecture > Completed Project Threads Archive
Forum Jump



Forum Jump


All times are GMT. The time now is 8:58 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.