New Austonian Construction Report:
http://www.theaustonian.com/pics/2008-01-28_Austonian_Report_19.pdf
(Includes a good number of photographs)
From the report:
Work activities completed through
January 25, 2008:
Mat slab excavation complete and material removed from site
Mud slab poured at mat slab to facilitate reinforcing steel installation
Rebar crew currently installing 2nd layer of steel for mat slab
Slab pour to be completed on Saturday 2-2-08 or 2-9-08 contingent on weather
Perimeter concrete wall footings 75% complete
Wall forming of basement walls to begin next week
Pier caps 80% complete
Concrete foundation for tower crane #2 in progress
Tower crane #2 structural base to be delivered and installed next week
Sub grade preparations and compaction operations in progress for B-1 slab
Waterproofing of below grade walls started on 1-20-08
Utility work along Congress Avenue begins on 1-24-08
Blockout forms for elevator shafts being constructed on site
Compaction operations at sump pits in progress
Coordination and preparations for under slab plumbing rough-in underway
Painting of barricades along Congress Avenue in progress
Lighting installed in Congress Avenue pedestrian tunnel