As some of you may know, I work for Kirkland & Ellis. I received an email today in regard to our move to 300 N. Lasalle and thought I'd share a few tidbits. We are scheduled to relocate in the first quarter of 2009.
Builders continue to work on pouring the concrete core of the building. It takes about 1 week to pour a floor and 15 floors have been completed so far.
-The anticipated completion date of this phase is first quarter of 2008.
-The installation of steel will begin in late June/early July.
-The installation of the curtain wall is scheduled to begin in September.