Clock ticking on LRT
The proposed route for the Evergreen Line, from Lougheed Town Centre to Coquitlam.
At a closed-door TransLink meeting last Saturday, Tri-City mayors and their Pitt Meadows and Maple Ridge counterparts vowed to ramp up their lobbying efforts to get the light-rail line on track.
TransLink is short $400 million for the $970-million Evergreen Line, which is planned to run from Lougheed Town Centre in Burnaby to Douglas College in Coquitlam, and requires cash from senior governments.
TransLink spokesperson Ken Hardie said the regional transportation body will push the Evergreen Line as a “ready-to-go” project when the federal government tables its budget, expected in March.
TransLink has issued an April 1 deadline to get extra funding from Ottawa and Victoria. Otherwise, the line is dead.
Pressure from area mayors comes as TransLink faces growing opposition to the line and as the provincial government is poised to re-organize TransLink under a new governance model.
Port Moody Mayor Joe Trasolini said the northeast region could lose the $400-million TransLink has budgeted for the line.
“If senior governments don’t help us with the funding,” he said, “there are other areas in the Lower Mainland that are just waiting to pounce on the $400 million TransLink has put aside for Evergreen.
“We have been battling for 20 years for a line,” Trasolini said, “and I know the TransLink board is going to look at it as a defeat if, by April 1, we don’t have the funding because it will be dead.”
Coquitlam Mayor Maxine Wilson said the clock is ticking.
“Decision time is soon. My sense is that we have good relationships with both levels of government on this,” she said.
“Clearly, from all indications to date, we’ve not hit any barriers,” Port Coquitlam Mayor Scott Young said. “But we’ve yet to receive a green light either, and that’s what we find most troubling at this particular juncture as we get down to the wire. We need to get some positive feedback that would clearly indicate that we can advance with the project.”
Maple Ridge Mayor Gordon Robson said he’s pressing MPs and MLAs “to make sure they understand the area wants this done. Maple Ridge can’t have an extension to the Evergreen Line until it’s built.”
Trasolini also said development in the Tri-Cities, which has been building in anticipation of the rail transit, may slow if Evergreen fails.
Last fall, Trasolini suggested if senior government funding didn’t come through, he would stop development in his city, thereby holding up the GVRD’s plan to double the population in every city in the Lower Mainland by 2020.
Conservative Tri-City MP James Moore said the mayors are doing the right thing by joining forces to support the line.
“I have always strongly believed in rapid transit to our community,” he said. “With our growing density and the number of residents who commute outside of the Tri-Cities daily, rapid transit is in our best interest.”
The mayors’ renewed pleas came as TransLink held an open house for Tri-City residents on the Evergreen Line last Saturday. The meeting, which took place at Coquitlam city hall, featured presentations from international transportation experts Troy Russ and Alan Jones, both consultants on the Evergreen Line.
Russ said the Evergreen Line “isn’t just to get people from A to B but also to serve the community’s needs.”
He said 70% of all car journeys are to make errands three miles from home.
“LRT is the perfect match for ridership demand in the northeast sector,” added Fred Cummings, TransLink vice-president of major construction projects.
Still, residents raised concerns about the impact of Evergreen, especially when construction is set to start in September. Business owners at the meeting said building Evergreen would have a severe effect on their bottom line.
“It’s not going to be a completely zero impact,” Cummings said of construction, adding, “A traffic management plan is critical to address the concerns. We are going to do everything in our power to mitigate [the impact].”
TRANSLINK Q&A
The Tri-City News asked TransLink:
• If there are 400 LRT lines in the world, why are Montpelier, Strasbourg, Nottingham and Portland always used as examples?
“Tri-Met in Portland is often used as a North American example as their system closer resembles the European-type system we anticipate for the Evergreen Line... Montpelier and the other examples are often used because of their similarities to northeast sector (i.e., population) and are the better examples from many that best fits our vision of the Evergreen Line.”
• What efforts are being made to obtain private funding?
“TransLink is assessing the opportunity to include private equity in the project, either through direct investment or through development opportunities along the Evergreen Line. We are in the very early stages on this assessment and have not even determined if these options are viable or not. But the goal is to decrease the funding gap and lessen the dependence on senior governments.”