Did the gantry crews take some holidays time because it seemed like they all have slowed down progress. They were going at a pretty good speed there for a while and now they haven't move much in the last few weeks.
|
Langley Luncher made very decent progress since my last update four weeks ago, advancing by 10 spans
Surrey Sprinter was the slowest gantry this time, even slower than Clayton Clipper, mainly due to the long span at 96 Avenue
Fleetwood Flyer is making decent progress as well
Not bad overall! By the September–October update, at least one of the gantries should have reached another station!