South Lamar Boulevard Getting Bike Lanes, Sidewalks, and Rain Gardens After Decade of Delays

Quote:
One of Austin's busiest and most dangerous corridors is finally getting the overhaul voters approved a decade ago. South Lamar Boulevard, a 1.5-mile stretch running from US 290 to Montclaire Street, is set for a ground-up redesign that will add dedicated bike lanes, ADA-compliant shared-use paths, upgraded bus stops, rain gardens, and new tree plantings.

The reconstruction targets infrastructure that hasn't kept pace with the neighborhood around it. South Lamar transformed over the past 15 years from a low-slung commercial strip into one of Austin's densest mixed-use corridors, filled with apartments, restaurants, and entertainment venues. The road itself stayed largely a 1960s-era arterial: narrow, broken sidewalks, no continuous bike facilities, and a crash rate bad enough to land it on Austin's High-Injury Network, the roughly 8 percent of city streets that account for more than 68 percent of serious injuries and fatalities.

The project is part of Austin's Corridor Construction Program, which voters funded through the 2016 Mobility Bond and a follow-on 2020 bond, together committing roughly $1.1 billion to redesigning major arterial roads into what planners call "complete streets" that serve pedestrians, cyclists, and transit riders alongside drivers. South Lamar was named as a priority corridor in the original 2016 package. The solicitation is now posted on the city's procurement portal, with bids due Sept. 3, 2026.
__________________
HAIF
Reply With Quote
     
     
  #10062  
Old Posted Aug 14, 2026, 3:09 PM
atxsnail atxsnail is offline
Registered User
 
Join Date: Feb 2014
Posts: 608
what in the generative AI nonsense is going on in this article's picture?
Reply With Quote
     
     
  #10063  
Old Posted Aug 14, 2026, 3:18 PM
Croon Croon is offline
Registered User
 
Join Date: Jun 2024
Posts: 74
Quote:
Originally Posted by atxsnail View Post
what in the generative AI nonsense is going on in this article's picture?
Oh God I hate it. Especially in real estate/development articles/social media reels. Please use official/accurate renders/mockups or nothing at all.

There's a guy in town on FB and Instagram, nearly every reel features an AI render/mock up/cityscape image of Austin that is clearly AI.
Reply With Quote
     
     
  #10064  
Old Posted Aug 14, 2026, 4:21 PM
The ATX's Avatar
The ATX The ATX is offline
Moderator
 
Join Date: May 2006
Location: Right here, right now
Posts: 12,824
I'm just glad that we can still identify AI generated nonsense in journalism. It's going to get much worse in a few years.
__________________
Follow The ATX on X:
https://x.com/TheATX1

Things will be great when you're downtown.
Reply With Quote
     
           
     
  #10066  
Old Posted Aug 22, 2026, 5:36 PM
ATX2030 ATX2030 is offline
Registered User
 
Join Date: Nov 2020
Posts: 1,008
Studies say Austin-San Antonio passenger rail requires $13 billion or a route Union Pacific resists

KUT 90.5 | By Nathan Bernier
Published August 20, 2026 at 5:36 PM CDT

https://www.kut.org/transportation/2026-...ail-txdot-travis-county-study-13-billion

A passenger rail link between Austin and San Antonio, long dreamed about by local officials and commuters who would rather watch YouTube than white-knuckle it between semi-trucks on I-35, is now being presented with two very different paths forward.

But the cheaper of those two paths is already running into the same obstacle that helped kill the last serious effort: Union Pacific says its freight railroad still doesn't have capacity for any more passenger trains beyond the extremely limited existing service. Amtrak's slow rolling Texas Eagle runs only once a day, and even that service arrives on schedule just 56% of the time.

The other option would build an all-new, mostly elevated railroad starting at Austin-Bergstrom International Airport and following State Highway 130 to Interstate 10. That avoids Union Pacific but bypasses the biggest population centers between Austin and San Antonio. It also comes with a much heftier price tag: $13.5 billion.

The two choices are laid out in separate studies released this summer, both prepared by engineering firm HNTB. TxDOT published a study in June that considered adding passenger trains to the existing Union Pacific corridor.

This week, Travis County released the study on whether a new railroad could be built along SH 130 and I-10. The 62-page report cost almost $125,000.

At a high level, engineers found either concept could work. But the studies also exposed the tradeoffs that have prevented Austin-San Antonio passenger rail from becoming a reality, despite millions of dollars spent on studies and planning.

On paper, the Union Pacific option is more affordable. TxDOT studied running up to eight round trips a day between Austin and San Antonio, with stops in New Braunfels and San Marcos. The most ambitious scenario would require almost $1.9 billion in new tracks, signals, stations and other infrastructure. Annual operation and maintenance costs could top $61 million.

But that study came with an major limitation: Union Pacific declined to participate. So TxDOT had to make assumptions about how passenger and freight trains could use the railroad by relying on federal data and "engineering judgment."

Union Pacific is now making clear it disagrees with the premise of the study.

"Past efforts have found the existing freight corridor is not sufficient to accommodate both freight and passenger demand," Union Pacific spokesperson Robynn Tysver told KUT News on Thursday. "We believe that is still the case today and we are focused on serving our customers and taking trucks off the state's congested highways."

That response came hours after Travis County Judge Andy Brown told KUT News that his understanding from previous conversations with Union Pacific was that the railroad could be willing to negotiate again if officials found a real source of money.

Brown still called the Union Pacific route "probably more realistic in the short term" because of its lower price and its ability to serve the communities between Austin and San Antonio.

The SH 130 to I-10 option studied by Travis County avoids the need to cooperate with Union Pacific, but introduces several other problems.

HNTB estimates nearly 54 miles of the roughly 90-mile route would have to be elevated. The $13.5 billion estimate, which doesn't account for any inflation, includes a 45% cost cushion known as a "contingency."

Unlike the plan studied by TxDOT, the price tag includes $360 million for six trains, each with two locomotives and three coach cars, plus a $300 million operations and maintenance facility.

The estimate also assumes minimal highway reconstruction or land acquisition, and doesn't include interest on any potential debt.

Running the trains could cost another $140 million to $190 million each year. The Travis County study didn't forecast ridership, so it also can't say how much fare revenue could offset those costs.

Brown argues the political climate has shifted, pointing to support from county judges, TxDOT's renewed interest in passenger rail and conversations with state lawmakers and U.S. Sen. Ted Cruz.

But there's plenty of history for skeptics to point to. By 2016, the Capital Area Metropolitan Planning Organization had counted 24 studies looking into commuter rail between the Austin-area and San Antonio since 1997.

The Lone Star Rail effort had spent about $23 million in state and federal money before Union Pacific ended its agreement with the rail district a decade ago.

For now, one of the two paths for an Austin-San Antonio passenger rail requires Union Pacific to reverse its position. The other needs billions of dollars with no funding committed.


More background

https://www.kxan.com/traffic/transportat...enger-rail-line-viable-for-13-5-billion/
Reply With Quote
     
     
  #10067  
Old Posted Aug 22, 2026, 7:50 PM
Lobotomizer's Avatar
Lobotomizer Lobotomizer is offline
Frontal Lobe Technician
 
Join Date: Jul 2021
Posts: 523
I just looked through the preliminary schematics for the I-35 expansion through Round Rock and Georgetown, and WOW they're going BIG. It includes four elevated lanes from 45N to 1431, similar to what's going up in South Austin. It also includes flyovers to and from 79. The amount of bridge work through this section is incredible, and I counted a total of 26 lanes going over McNeil. This will definitely cost in excess of $1 billion, and maybe closer to $2 billion.

I know it's not something most here would be interested in, but with what's already being built through Travis County, I-35 through the Austin metro will be one of the most insane stretches of highway I've ever seen.
__________________
Aw, snap! You just got Lobotomized!
Reply With Quote
     
     
  #10068  
Old Posted Sep 8, 2026, 8:00 PM
lonewolf lonewolf is offline
Registered User
 
Join Date: Oct 2012
Posts: 621
I have in my notes to be on the lookout for the completion of the MLk bridge over I-35 this month.

this IG post from 3 weeks ago is the only recent update I can find on it https://www.instagram.com/reel/Db_vJTTzXcp/

Does anyone who frequents the area think it will be fully (or 99%) functional by end of this month?
Reply With Quote
     
     
  #10069  
Old Posted Sep 8, 2026, 8:21 PM
The ATX's Avatar
The ATX The ATX is offline
Moderator
 
Join Date: May 2006
Location: Right here, right now
Posts: 12,824
Quote:
Originally Posted by lonewolf View Post
I have in my notes to be on the lookout for the completion of the MLk bridge over I-35 this month.

this IG post from 3 weeks ago is the only recent update I can find on it https://www.instagram.com/reel/Db_vJTTzXcp/

Does anyone who frequents the area think it will be fully (or 99%) functional by end of this month?
The seven traffic lanes have been open for a few weeks. By "finished" maybe they mean pedestrian and bike lane related touches. A couple CCTV cams show it:

https://cctv.austinmobility.io/image/1461.jpg
__________________
Follow The ATX on X:
https://x.com/TheATX1

Things will be great when you're downtown.
Reply With Quote
     
     
  #10070  
Old Posted Yesterday, 7:40 PM
freerover freerover is offline
Registered User
 
Join Date: Nov 2017
Posts: 2,398
Quote:
Originally Posted by Lobotomizer View Post
I just looked through the preliminary schematics for the I-35 expansion through Round Rock and Georgetown, and WOW they're going BIG. It includes four elevated lanes from 45N to 1431, similar to what's going up in South Austin. It also includes flyovers to and from 79. The amount of bridge work through this section is incredible, and I counted a total of 26 lanes going over McNeil. This will definitely cost in excess of $1 billion, and maybe closer to $2 billion.

I know it's not something most here would be interested in, but with what's already being built through Travis County, I-35 through the Austin metro will be one of the most insane stretches of highway I've ever seen.
We don't even know yet how much the central portion is going to cost. They've been saying 4 billion since 2020. It's not 4 billion. The contracts should get finalized and go out in the next few years.
Reply With Quote
     
     
  #10071  
Old Posted Yesterday, 10:39 PM
Lobotomizer's Avatar
Lobotomizer Lobotomizer is offline
Frontal Lobe Technician
 
Join Date: Jul 2021
Posts: 523
Should be a lot sooner than that, as the portions from 290E to Holly St. starts next year. At that point all of I-35 in Travis County will be u/c which will be nuts.
[IMG][/IMG]
__________________
Aw, snap! You just got Lobotomized!
Reply With Quote
     
     
  #10072  
Old Posted Yesterday, 11:14 PM
freerover freerover is offline
Registered User
 
Join Date: Nov 2017
Posts: 2,398
Quote:
Originally Posted by Lobotomizer View Post
Should be a lot sooner than that, as the portions from 290E to Holly St. starts next year. At that point all of I-35 in Travis County will be u/c which will be nuts.
[IMG][/IMG]
So there are multiple contracts going out. The pre-con contracts go out next year but the main work doesn't go out until Sept 2028 for the University Section and Sept 2029 for the Downtown section.


https://www.txdot.gov/content/dam/projec...ntral-technical-schedule-september05.pdf
Reply With Quote
     
     
  #10073  
Old Posted Yesterday, 11:39 PM
Riverranchdrone Riverranchdrone is offline
Registered User
 
Join Date: Aug 2017
Location: Austin
Posts: 1,086
We all know these are decades over due but damn!. Pretty much stay off of IH35 for the next decade.
Reply With Quote
     
     
  #10074  
Old Posted Today, 1:39 AM
freerover freerover is offline
Registered User
 
Join Date: Nov 2017
Posts: 2,398
Quote:
Originally Posted by Riverranchdrone View Post
We all know these are decades over due but damn!. Pretty much stay off of IH35 for the next decade.
I really don't think 90% of people. understand how fucked it's going to be to take a highway that is mostly at grade or elevated and sink it 30 feet. You're talking about crossings like Holly and Cesar closed for 6 months to a year. It's not like replacing the MLK bridge when you have to dig out under the existing bridge or turn an at grade crossing into a bridge. I mean I'm sure they will alternate adjacent closures like they did in Houston for Katy but it's still going to suck.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > United States > Texas & Southcentral > Austin
Forum Jump



Forum Jump


All times are GMT. The time now is 12:07 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.