Originally Posted by sailor734
Has building one really been under construction for 3 years? CMHC says the average time from groundbreaking to occupancy for a six story residential is 22 months and AI says the normal range is 18 to 24. Intuitively I always thought this build was moving slowly but perhaps it actually is?
|
The 3 year figure isn't quite right, the foundation and underground parking level work only started in the second half of 2024, so about 24 months ago, and the steel was late last spring. The pilings were in almost a year before that, but there was still a lot of site and wharf infrastructure work going on by the city and its contractors at that time and that held up the building construction starting.
It's tough to compare this building time to other sites because of the complexity of the concurrent upgrades to the seawall and wharf, it's quite different than just building on a typical lot somewhere that isn't on reclaimed land on the ocean.