Wrapping up the 7th floor concrete block walls and posts. Have now installed a exterior construction elevator on the west side. The 8th floor precast concrete floor slabs have started being installed and work on building the 8th floor concrete block walls has started on the south end..
Last edited by jammer139; Sep 6, 2026 at 8:03 PM.
|