Quote:
Originally Posted by jammer139 View Post
Contract award for the Wellington phase from Watson to Baseline.


a) the bid submitted by Bre-Ex Construction Inc. at its tendered price of $50,416,071.33 excluding HST, for the Wellington Gateway and Municipal Infrastructure Improvements Phase 2B – Base Line Road to Watson Street project, BE ACCEPTED; it also being noted that the bid submitted by Bre-Ex Construction Inc. was the lowest of four (4) bids received and meets the City's specifications and requirements in all areas;

b) Dillon Consulting Limited BE AUTHORIZED to carry out the construction inspection and contract administration for the said project in accordance with the estimate, on file, at an upset amount of $4,802,873.13 excluding HST, in accordance with Section 13.3 iii) (a) of the City of London’s Procurement of Goods and Services Policy;


https://pub-london.escribemeetings.com/filestream.ashx?DocumentId=124294
When will this start? Commissioners and Wellington is already a mess, so ripping up the Base Line intersection will only make things minimally worse. I am surprised they didn't start both of them at the same time.

My guess is ambulances needing a somewhat reliable to way to reach Vic Hospital? Keeping an intersection construction free sounds good for that in theory, but since it's congested at all sides due to backup resulting from construction at another nearby, its kinda pointless for many hours of the day.
__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #1362  
Old Posted Jun 22, 2026, 11:09 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,132
So a little bit of rain early this morning and no signs of any workers on the Wellington St BRT project. Anyone with a phone could see the light rain was ending in south London by around 8:30am but the contractors doing our road projects had already called it a day.


It's no wonder this construction is taking so long and behind schedule.
Reply With Quote
     
     
  #1363  
Old Posted Jun 23, 2026, 2:49 PM
MolsonExport's Avatar
MolsonExport MolsonExport is offline
Touching grass everyday.
 
Join Date: Oct 2003
Location: Otisburgh
Posts: 51,176
Just get Josh out there with his construction helmet for a photo op, and the site will again be humming with "activity".
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell). Sweet Loretta fart thought she was a cleaner, but she was a frying pan. (John Lennon)
Reply With Quote
     
     
  #1364  
Old Posted Jun 27, 2026, 12:08 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,132
They have done the traffic lane shift on Highbury over the CP tracks to the new west side of the overpass. Just started on the east side bridge deck removal.
Reply With Quote
     
     
  #1365  
Old Posted Jul 7, 2026, 1:16 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,132
Overnight closures to top coat pave Wellington St over the Clark Bridge.

https://www.cbc.ca/news/canada/london/cl...-on-wellington-gateway-project-9.7259695
Reply With Quote
     
     
  #1366  
Old Posted Jul 17, 2026, 7:42 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,132
They have started installing the top coat of asphalt on the west bound side of Oxford St E between Second and Highbury. Have been installing steel posts between the masonry posts for the fence between the College buildings and Oxford St. Looks like they definitely want to finish the westbound lanes of Oxford and get the College fencing and landscaping installed before the start of the new school year.
Reply With Quote
     
     
  #1367  
Old Posted Jul 17, 2026, 9:05 PM
Djeffery's Avatar
Djeffery Djeffery is offline
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 6,250
They even have lanes painted on the westbound side. Looked like the permanent lane markings, although one would have to assume they plan to shift eastbound traffic over there at some point to pave those eastbound lanes. Unless they are going to try to squeeze a lane of traffic on the eastbound side and also pave a lane as they go.
Reply With Quote
     
     
  #1368  
Old Posted Jul 23, 2026, 8:38 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,132
They have now done the traffic lane shift to the west bound side of Oxford St from Second to Highbury. Still have a section of the new College fencing to install. Already installing landscaping along the fencing in front of the college. Hopefully they quickly finish off the eastbound side of Oxford St by the end of this year.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 1:39 AM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.