I found a recent article with some info and updated renderings...

https://renx.ca/parkit-enters-jv-to-develop-2-tower-multifamily-site-in-london

This will be a "three-way partnership." "Two [London-based] companies, Decade Capital and Southside Group, will each take 25 per cent stakes in the venture, which is known as 760 Second Street Partnership.

Vancouver-based Parkit owns the other 50 per cent of the venture."

Reply With Quote
     
     
  #22  
Old Posted Dec 21, 2025, 1:21 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
Good to hear that as at least Southside is a real developer. It appears they are working on forming something now which could be a tower crane base for the north tower. Not clear if they will have underground parking below these towers.
Reply With Quote
     
     
  #23  
Old Posted Jan 12, 2026, 8:00 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
Forming now the foundation footing floating raft slab on the north end of the north tower. Does not appear that they will have an underground level of parking. Small mobile crane being used for the work so far as they don't appear to have the tower crane base poured yet. This will likely be the second tower crane of 2026 to go up in London.
Reply With Quote
     
     
  #24  
Old Posted Jan 16, 2026, 10:08 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
More excavation work for the foundation of the north 15s tower with digging on the south end. Forming for the foundation continues but still no sign of tower crane prep. Apparently they intend to build the first building before green lighting tower two. Might be waiting to see how well the first building rents before committing to construction of tower 2.
Reply With Quote
     
     
  #25  
Old Posted Jan 31, 2026, 11:48 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
They assembled the 2nd tower crane of this year in London today. Steel rebar going in for ground floor walls and posts.
Reply With Quote
     
     
  #26  
Old Posted Feb 23, 2026, 10:02 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
First ground floor walls are now poured on the north end.
Reply With Quote
     
     
  #27  
Old Posted Mar 29, 2026, 5:48 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
Looks like they have wrapped up forming and pouring all the ground floor walls and posts. No signs yet how they plan to do the 2nd floor slab. Whether they intend to form and pour a concrete slab or use precast concrete slabs.
Reply With Quote
     
     
  #28  
Old Posted Apr 8, 2026, 8:34 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
They have now installed about 60% of the second floor slab using precast concrete floor slabs. Looks like they will go with poured and formed walls and posts and precast for the floor slabs on this 15s building.
Reply With Quote
     
     
  #29  
Old Posted Apr 21, 2026, 3:57 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
Have now poured 50% of the second floor walls and posts and forming for the remainder of the 2nd floor is nearly done.
Reply With Quote
     
     
  #30  
Old Posted Apr 26, 2026, 3:11 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
Almost done forming and pouring the 2nd floor walls and posts on this 15s mid rise apartment. Should wrap that up this week and start installing the 3rd floor precast concrete floor slabs. I suspect they will settle into a 2 floors every 7 weeks pace as it's just rinse and repeat now up to the top.
Reply With Quote
     
     
  #31  
Old Posted May 1, 2026, 10:48 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
Have finished installing the 3rd floor precast concrete floor slabs and have made alot of progress forming for 3rd floor walls and posts.
Reply With Quote
     
     
  #32  
Old Posted May 16, 2026, 6:06 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
Have now started installing the 4th floor precast concrete floor slabs on the north end.
Reply With Quote
     
     
  #33  
Old Posted May 24, 2026, 11:53 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
Have now installed the 4th floor precast floor slabs and have started forming for the 4th floor walls and posts on the north end.
Reply With Quote
     
     
  #34  
Old Posted May 30, 2026, 12:25 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
About 70% of the 4th floor walls and posts are now poured. Should wrap up the 4th floor next week and start installing the 5th floor precast concrete floor slabs.


EllisDon Forming signs up on the fencing.

Last edited by jammer139; May 30, 2026 at 2:58 AM.
Reply With Quote
     
     
  #35  
Old Posted Jun 6, 2026, 7:18 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
About 50% of the 5th floor precast concrete floor slabs now installed.
Reply With Quote
     
     
  #36  
Old Posted Jun 13, 2026, 11:34 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
Forming and pouring for the 5th floor walls and posts is progressing fast on this 15s north building.
Reply With Quote
     
     
  #37  
Old Posted Jun 24, 2026, 6:38 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 8,954
Have started installing the concrete floor slabs for the 6th floor on the north end and have started setting up 6th floor wall forming.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 4:29 AM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.