When can we expect 11th and Front to submit its design review? Even though it’s all up in the air, are there any deadlines officially or unofficially to be aware of?
|
The last official update is from last December. They submitted a Conditional Use permit which the city approved, which states that they have no more than 2 years to act upon it before it expires. As far as I can tell, this is the furthest out deadline for the project, putting it at around the middle of December, 2027. They still need to present their final design to the Design Review Commission.
For context, there was around 14 months between the final design documents submitted for The Arthur (September 2021) and when they broke ground (November 2022), according to BoiseDev. Obviously the cost of, well, everything has gone up a lot in the last year, slowing down updates (same thing happened to the Arthur).
This is my understanding at least, if anyone else has a better understanding of it then that would be great.