For those interested in the Housing Accelerator Fund.
The City has recently received its third installment of $30.6 million from the Housing Accelerator Fund. Unlike rounds one and two, the third and fourth installments will not include a large capital grant program for developers.
Last year council had allocated $12 million from the 3rd installment, to funding the
Multi-Family Sustainable Housing Infrastructure Program (MSHIP). This program was to help developers upgrade local water, wastewater, and drainage systems in areas where old infrastructure blocks new high-density multi-family housing, it had hopes of unlocking up to 1,200 new units. Applications opened in June 2025 and closed in September 2025, only one application qualified. $1.18 million was awarded to a 118 unit development at Markham Road and Gull Lake Road, next to the Rapid Transit Marham Station..
On November 27, 2025,
City Council approved shifting some of the funds from the MSHIP to other local infrastructure improvements to support housing, including:
- Up to $8.3 million be allocated from the Multi-Family Sustainable Infrastructure Grant to the following projects, to undertake works supporting local municipal infrastructure improvements:
A. 825 Taché Avenue
B. 1350 Pembina Highway and Crane Street
C. 1350 Pembina Back-lane improvement
- Up to $2 million be allocated from the Multi-Family Sustainable Infrastructure Grant to undertake the pilot catch basin program to be undertaken by the Water and Waste Department.
Here is a breakdown of Winnipeg's $122.4M HAF funding budget:

As of the November 2025 report, $14 million in the General fund remained unallocated. Since then, Council approved $5 million from the fourth instalment payment for the Marlborough development. This brings the total unallocated HAF funding across all four rounds to approximately $9 million.