February update
Construction of the Project continues to advance in line with the timeline outlined in the Final Prospectus.
Since our previous update, the parkade structure up to P1 has now been completed and Level 1 slab
formwork is underway. We anticipate pouring the Level 1 slab in March 2026, positioning the Project to
transition to above grade work in Q2 2026.
Concrete works commenced in early November 2025 and remain on schedule. To date, approximately 12,500
cubic metres of concrete have been poured. Throughout 2026 and into early 2027 concrete for the podium
structure of the building containing the hotel will be progressing.
Design development of the hotel continues to progress, with the team planning to build out the model suites
onsite during the first half of 2027.
No new contracts were awarded since our last update, tendering activity remains on track, with approximately
76% of trade contracts awarded. The remaining scopes are primarily related to finishing work and will be
tendered in upcoming stages as construction progresses toward the above-grade structure.
|