Hopefully this project has nothing to do with Schmuel Parkinglot Farhi
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell). Sweet Loretta fart thought she was a cleaner, but she was a frying pan. (John Lennon)
Reply With Quote
     
     
  #82  
Old Posted Aug 10, 2025, 8:04 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,294
Drilling rig now working the north side perimeter after most of the east side appears to be done.
Reply With Quote
     
     
  #83  
Old Posted Aug 13, 2025, 1:24 AM
CharlesSaticoy CharlesSaticoy is offline
Registered User
 
Join Date: May 2022
Posts: 38
Hopefully they don’t use those stupid neon lights on this one.
Reply With Quote
     
     
  #84  
Old Posted Aug 23, 2025, 7:08 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,294
Looks like they have started on the west side pilings along the existing foundation of the hotel. Would imagine this will be more exacting to avoid damage and vibration to the hotel underground parking and foundation.
Reply With Quote
     
     
  #85  
Old Posted Aug 23, 2025, 9:58 PM
GreatTallNorth2 GreatTallNorth2 is offline
Registered User
 
Join Date: May 2006
Posts: 1,758
I see they have been approved by the city for the pouring of the foundation, is it a step process for approval?
Reply With Quote
     
     
  #86  
Old Posted Aug 24, 2025, 7:35 PM
Snark Snark is offline
Registered User
 
Join Date: May 2006
Posts: 505
Quote:
Originally Posted by GreatTallNorth2 View Post
I see they have been approved by the city for the pouring of the foundation, is it a step process for approval?
Yes, part of the larger process. It means construction if the main structure can begin.
Reply With Quote
     
     
  #87  
Old Posted Sep 10, 2025, 12:26 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,294
Interesting news about the conversion of some of the Hilton Hotels units to apartments. Next door the installation of the pilings for the excavation of the pit continues along the north side.

https://lfpress.com/news/local-news/hote...it-market-as-apartments?itm_source=index
Reply With Quote
     
     
  #88  
Old Posted Sep 19, 2025, 1:23 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,294
Now working the south side perimeter with the drilling rig for the caisson pilings.

Last edited by jammer139; Oct 4, 2025 at 6:19 PM.
Reply With Quote
     
     
  #89  
Old Posted Sep 27, 2025, 3:18 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,294
Have started excavating in the NW corner and are about 2 meters deep. Still have alot of the south side to drill and install pilings for.
Reply With Quote
     
     
  #90  
Old Posted Oct 20, 2025, 9:18 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,294
Drilling rig now installing the pilings in the SE corner of the lot. Could be wrapping up soon. Excavator has been digging the pit along the north side down to around 3m. Should see the tie back drilling machine installing those in prep for shoring and corner brace structural steel.
Reply With Quote
     
     
  #91  
Old Posted Nov 12, 2025, 7:29 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,294
They have now dug down 3m along the south side of pit exposing the pilings. Drilling rig machine has been down in the pit drilling pilings along the west wall of pit up against the foundation of the underground parking of the hotel. Machine has been drilling into the pit wall to install the cable tie back anchors into the pit wall along the north and east side of pit that isn't blocked by the dirt ramp used to access the bottom of the pit.
Reply With Quote
     
     
  #92  
Old Posted Nov 14, 2025, 2:44 PM
GreatTallNorth2 GreatTallNorth2 is offline
Registered User
 
Join Date: May 2006
Posts: 1,758
When do we expect to see a crane up on this site?
Reply With Quote
     
     
  #93  
Old Posted Nov 14, 2025, 4:10 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,294
Unless they plan to mount the tower crane base outside the foundation pit walls, I would think they will need to excavate the full 2s depth of the pit first and pour the tower crane base in the pit itself. Will be interesting to see where they setup the crane given how close the Delta and Doubletree Hotels stand. To swing the horizontal jib type of crane they will need to set it up taller then the two hotels. Or they might go with a luffing jib type used in tight spaces. They still have to dig the pit much deeper yet to clear two levels of underground parking and built a foundation. Probably looking at 7-8m deep all told.
Reply With Quote
     
     
  #94  
Old Posted Nov 18, 2025, 7:12 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,294
The Caisson piling drilling rig machine has done its work and has been removed from the site. Focus will now shift to excavating the first 3m of the pit and installing the tie backs into the pit walls and installing shoring before digging out the next 3m of the pit.
Reply With Quote
     
     
  #95  
Old Posted Dec 7, 2025, 3:06 AM
GreatTallNorth2 GreatTallNorth2 is offline
Registered User
 
Join Date: May 2006
Posts: 1,758
There is no diagram of this building and it is not listed in the London database on SSP or in Wikipedia. I am not sure how one edits those pages but this building is u/c and will be London's 3rd tallest when complete at 109 metres tall.
Reply With Quote
     
     
  #96  
Old Posted Dec 21, 2025, 7:47 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,294
Should see excavator and dump trucks soon to start digging out the final few meters of the pit as they appear to be nearly done installing the pit wall tie backs and shoring at the current depth.
Reply With Quote
     
     
  #97  
Old Posted Jan 13, 2026, 5:36 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,294
Digging the pit deeper along the west and north side with parade of dump trucks hauling away dirt.
Reply With Quote
     
     
  #98  
Old Posted Feb 5, 2026, 9:02 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,294
Looks like Holloway Lodgings has decided to go with Magil Construction as the general contractor on this 35s build. Their signs are up all over the construction fencing now.

https://www.magil.com/en/projects
Reply With Quote
     
     
  #99  
Old Posted Feb 6, 2026, 2:50 PM
GreatTallNorth2 GreatTallNorth2 is offline
Registered User
 
Join Date: May 2006
Posts: 1,758
Quote:
Originally Posted by jammer139 View Post
Looks like Holloway Lodgings has decided to go with Magil Construction as the general contractor on this 35s build. Their signs are up all over the construction fencing now.

https://www.magil.com/en/projects
Any sign of a crane going up soon?
Reply With Quote
     
     
  #100  
Old Posted Feb 7, 2026, 12:20 AM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,294
I suspect they are still digging the pit down to the final depth. Will then drill in the tie backs in the pit wall and install shoring eventually digging out the dirt ramp access. Curious to see where they end up locating the tower crane base for this build and which type of crane they use.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 7:18 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.