HomeDiagramsDatabaseMapsForum About
     

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation


Reply

 
Thread Tools Display Modes
     
     
  #1501  
Old Posted Nov 25, 2025, 12:45 PM
VANRIDERFAN's Avatar
VANRIDERFAN VANRIDERFAN is offline
Registered User
 
Join Date: Jan 2007
Location: Regina
Posts: 5,431
So, using this logic the western extension will maybe be ready by 2030?
Reply With Quote
     
     
  #1502  
Old Posted Nov 25, 2025, 1:18 PM
J.OT13's Avatar
J.OT13 J.OT13 is online now
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,635
I have more faith in the east-west contractors than SNC.
Reply With Quote
     
     
  #1503  
Old Posted Dec 15, 2025, 1:47 PM
sseguin sseguin is offline
Registered User
 
Join Date: Aug 2018
Posts: 287
Tracking the Progress: Ottawa’s O-Train Stage 2 Eastern Extension - December 2025
Video Link


Rail Fans Canada takes you trackside for an in-depth update on Ottawa’s expanding LRT system. In this December 2025 video, we show the latest progress on the O-Train Stage 2 East Extension, stretching from Blair Station to Trim Road in Orléans. With substantial completion just around the corner, and trial running likely to start shortly after, the Eastern Extension is in the final stages to opening, in early 2026.

Get a close-up look at station construction, trackwork, and what’s coming next as this vital light rail extension moves closer to completion. Whether you’re following the city’s transit evolution or just love all things rail, this is your go-to update for the O-Train East Extension.
__________________
Rail Fans Canada - https://www.RailFans.ca
Reply With Quote
     
     
  #1504  
Old Posted Dec 15, 2025, 3:53 PM
Truenorth00 Truenorth00 is offline
Registered User
 
Join Date: May 2017
Posts: 28,370
Quote:
Originally Posted by VANRIDERFAN View Post
So, using this logic the western extension will maybe be ready by 2030?
I don't buy their 2027 date at all. Fall 2028 is my bet.
Reply With Quote
     
     
  #1505  
Old Posted Dec 15, 2025, 11:44 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by Truenorth00 View Post
I don't buy their 2027 date at all. Fall 2028 is my bet.
Probably a resonable bet
Reply With Quote
     
     
  #1506  
Old Posted Dec 16, 2025, 6:30 PM
J.OT13's Avatar
J.OT13 J.OT13 is online now
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,635
O-Train East extension testing to begin ‘relatively early’ in 2026, mayor says

Josh Pringle, CTV
Published: December 16, 2025 at 11:18AM EST


Testing on the O-Train East extension into Orléans should begin “relatively early in the new year” but there is no “certain timetable” to open O-Train Line 1 in the east end, according to Mayor Mark Sutcliffe.

Work continues on the O-Train Line 1 extension from Blair Station to Trim Station after unspecified “deficiencies” were discovered by OC Transpo during a documentation review and on-site assessments this fall. OC Transpo told CTV News Ottawa the work to address included “specialized track infrastructure and sections of reinforced concrete.”

Appearing on Newstalk 580 CFRA’s The Morning Rush with Bill Carroll, Mayor Sutcliffe said the next phase of the preparations to open the O-Train East extension will begin in January.


“Relatively early in the new year, we’re going to see the testing happening,” Sutcliffe said Tuesday morning.

“You know you’ve got to meet certain criteria; once that’s done, we can open it to service.”

Interim Transit Services general manager Troy Charter told the Transit Committee on Nov. 24 that OC Transpo and its partners have made “significant progress towards completing the testing and commissioning.”

Charter suggested OC Transpo plans to open the O-Train East extension “early in the new year,” adding by the end of March is “achievable.”


Sutcliffe told CFRA, “The number one objective here is not to meet a certain timetable, as happened in the past.”

“But to open it when it’s ready, when it’s safe and when the people that we hired to build this service have delivered on their commitment to us, the residents and the taxpayers of Ottawa. We don’t want to take this off their hands until we’ve held them accountable and they’ve delivered the service, the infrastructure that we’ve paid for. It’s moving along; we’re making progress.”

The steps to launch O-Train Line 1 to the east end after substantial competition is achieved with construction include five to 10 days of pre-trial running, followed by the mandatory trial running that will last a minimum of 21 days.

The trial running period will “exercise and evaluate the performance” of the system’s infrastructure, vehicles, operating and maintenance personnel and operating procedures, according to staff.

Sutcliffe says the East extension will be a “game-changer” for O-Train Line 1.

“Line 1 right now, the first phase of that goes from Tunney’s Pasture to Blair. When you extend it all the way deep into Orléans, you’re going to see people in the suburbs of our city be able to use light rail to get downtown,” Sutcliffe said.

“At rush hour, they’re going to be able to do that in 35 to 40 minutes and they’re going to be zooming past cars that are stuck in traffic on the 174.”

Earlier this year, staff said the O-Train extension between Blair and Trim stations was expected to open by the end of 2025. The original plan called for the East extension to open in 2022, then the target date was moved to 2024.

https://www.ctvnews.ca/ottawa/articl...26-mayor-says/
Reply With Quote
     
     
  #1507  
Old Posted Dec 16, 2025, 6:41 PM
J.OT13's Avatar
J.OT13 J.OT13 is online now
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,635
Still stating that 2022 date that was always just A BAD ESTIMATE FROM STAFF and never what was was promised by the PEOPLE BUILDING IT. Considering the pandemic, two years late on a four year schedule isn't bad.
Reply With Quote
     
     
  #1508  
Old Posted Dec 16, 2025, 8:16 PM
BanjoUnchained BanjoUnchained is offline
Registered User
 
Join Date: Sep 2022
Location: ottawa
Posts: 44
Quote:
Originally Posted by J.OT13 View Post
Still stating that 2022 date that was always just A BAD ESTIMATE FROM STAFF and never what was was promised by the PEOPLE BUILDING IT. Considering the pandemic, two years late on a four year schedule isn't bad.
Ultimately it's just a failure of communication, your average layperson doesn't care. Most people couldn't tell you the difference between the owner, builder, maintainer etc.

A date was provided, it was missed and for your average person that's all that counts.
Reply With Quote
     
     
  #1509  
Old Posted Dec 16, 2025, 9:01 PM
J.OT13's Avatar
J.OT13 J.OT13 is online now
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,635
Quote:
Originally Posted by BanjoUnchained View Post
Ultimately it's just a failure of communication, your average layperson doesn't care. Most people couldn't tell you the difference between the owner, builder, maintainer etc.

A date was provided, it was missed and for your average person that's all that counts.
I do wish they didn't move the date a few months every time and provided one more realistic a couple years ago. This is nowhere near as bad as Stage 1 or Stage 2 south when they gave us obviously unrealistic dates (stations aren't even done, but sure, it should open next month ).
Reply With Quote
     
     
  #1510  
Old Posted Dec 17, 2025, 12:52 AM
ottawaballa ottawaballa is offline
Registered User
 
Join Date: Aug 2023
Location: Ottawa
Posts: 12
Quote:
Originally Posted by J.OT13 View Post
O-Train East extension testing to begin ‘relatively early’ in 2026, mayor says

Josh Pringle, CTV
Published: December 16, 2025 at 11:18AM EST


Testing on the O-Train East extension into Orléans should begin “relatively early in the new year” but there is no “certain timetable” to open O-Train Line 1 in the east end, according to Mayor Mark Sutcliffe.

Work continues on the O-Train Line 1 extension from Blair Station to Trim Station after unspecified “deficiencies” were discovered by OC Transpo during a documentation review and on-site assessments this fall. OC Transpo told CTV News Ottawa the work to address included “specialized track infrastructure and sections of reinforced concrete.”

Appearing on Newstalk 580 CFRA’s The Morning Rush with Bill Carroll, Mayor Sutcliffe said the next phase of the preparations to open the O-Train East extension will begin in January.


“Relatively early in the new year, we’re going to see the testing happening,” Sutcliffe said Tuesday morning.

“You know you’ve got to meet certain criteria; once that’s done, we can open it to service.”

Interim Transit Services general manager Troy Charter told the Transit Committee on Nov. 24 that OC Transpo and its partners have made “significant progress towards completing the testing and commissioning.”

Charter suggested OC Transpo plans to open the O-Train East extension “early in the new year,” adding by the end of March is “achievable.”


Sutcliffe told CFRA, “The number one objective here is not to meet a certain timetable, as happened in the past.”

“But to open it when it’s ready, when it’s safe and when the people that we hired to build this service have delivered on their commitment to us, the residents and the taxpayers of Ottawa. We don’t want to take this off their hands until we’ve held them accountable and they’ve delivered the service, the infrastructure that we’ve paid for. It’s moving along; we’re making progress.”

The steps to launch O-Train Line 1 to the east end after substantial competition is achieved with construction include five to 10 days of pre-trial running, followed by the mandatory trial running that will last a minimum of 21 days.

The trial running period will “exercise and evaluate the performance” of the system’s infrastructure, vehicles, operating and maintenance personnel and operating procedures, according to staff.

Sutcliffe says the East extension will be a “game-changer” for O-Train Line 1.

“Line 1 right now, the first phase of that goes from Tunney’s Pasture to Blair. When you extend it all the way deep into Orléans, you’re going to see people in the suburbs of our city be able to use light rail to get downtown,” Sutcliffe said.

“At rush hour, they’re going to be able to do that in 35 to 40 minutes and they’re going to be zooming past cars that are stuck in traffic on the 174.”

Earlier this year, staff said the O-Train extension between Blair and Trim stations was expected to open by the end of 2025. The original plan called for the East extension to open in 2022, then the target date was moved to 2024.

https://www.ctvnews.ca/ottawa/articl...26-mayor-says/
The Mayor's quote of "35 to 40 minutes", is he referring to the full length, or just Trim to downtown (assuming Parliament station)? If Trim to downtown, that would indicate a 43-48 minute full length trip. I hope it's on the lower end of that. I believe without slow zones, the original project agreement had an end to end runtime of under 40 minutes but I may be wrong.
Reply With Quote
     
     
  #1511  
Old Posted Dec 17, 2025, 2:31 AM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by ottawaballa View Post
The Mayor's quote of "35 to 40 minutes", is he referring to the full length, or just Trim to downtown (assuming Parliament station)? If Trim to downtown, that would indicate a 43-48 minute full length trip. I hope it's on the lower end of that. I believe without slow zones, the original project agreement had an end to end runtime of under 40 minutes but I may be wrong.
I assume downtown. Sadly, it seems our rickety flawed confederation line is still by far the fastest LRT line in the province, followed by the unhurried Trillium line.

If you listen hard you can still hear the grumbling down the road from the Finch LRT and it's whopping 11.8 km/h average speed

Something has gone horribly wrong with transit projects in this province
Reply With Quote
     
     
  #1512  
Old Posted Dec 17, 2025, 1:11 PM
J.OT13's Avatar
J.OT13 J.OT13 is online now
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,635
Quote:
Originally Posted by ottawaballa View Post
The Mayor's quote of "35 to 40 minutes", is he referring to the full length, or just Trim to downtown (assuming Parliament station)? If Trim to downtown, that would indicate a 43-48 minute full length trip. I hope it's on the lower end of that. I believe without slow zones, the original project agreement had an end to end runtime of under 40 minutes but I may be wrong.
I remember the Trim to Moodie run time was advertised as something like 52 minutes. Definitely under an hour. I'm assuming it will end up being an hour and a half or something ridiculous.

In my experience from Orleans (pre-pandemic), it took around half an hour tops to drive Downtown in the morning and short of an hour to drive back in the evening.
Reply With Quote
     
     
  #1513  
Old Posted Dec 17, 2025, 1:46 PM
kwoldtimer kwoldtimer is online now
Registered User
 
Join Date: Jan 2008
Location: La vraie capitale
Posts: 25,992
Quote:
Originally Posted by Truenorth00 View Post
I don't buy their 2027 date at all. Fall 2028 is my bet.
That would be, what, about three years late?
Reply With Quote
     
     
  #1514  
Old Posted Dec 19, 2025, 3:09 PM
J.OT13's Avatar
J.OT13 J.OT13 is online now
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,635
Quote:
Originally Posted by kwoldtimer View Post
That would be, what, about three years late?
Contractor promised 2026 initially.
Reply With Quote
     
     
  #1515  
Old Posted Jan 8, 2026, 3:44 PM
AuxTown's Avatar
AuxTown AuxTown is offline
Registered User
 
Join Date: Apr 2006
Location: Ottawa, Canada
Posts: 4,552
Any word on testing? The traffic coming from Orleans has apparently been terrible this week....would be a good time for them to see a train whizzing by!
Reply With Quote
     
     
  #1516  
Old Posted Jan 8, 2026, 5:32 PM
lrt's friend lrt's friend is online now
Registered User
 
Join Date: Dec 2006
Posts: 12,601
Quote:
Originally Posted by AuxTown View Post
Any word on testing? The traffic coming from Orleans has apparently been terrible this week....would be a good time for them to see a train whizzing by!
something tells me that traffic will be travelling faster than the train most of the time
Reply With Quote
     
     
  #1517  
Old Posted Jan 9, 2026, 3:03 PM
J.OT13's Avatar
J.OT13 J.OT13 is online now
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 27,635
Quote:
Originally Posted by lrt's friend View Post
something tells me that traffic will be travelling faster than the train most of the time
Well yes, outside rush hour for sure. For better or worse, it is designed for commuters in mind, and if the thousands of people on the 174 see the train going faster than them, then it could convince them to go to take the train next time.

The only stretches of the O-Train that might be used all day by people who chose transit over car at all times will be Algonquin to Hurdman and Bayview to Carleton. The rest of the system will be heavily commuter focused.
Reply With Quote
     
     
  #1518  
Old Posted Jan 9, 2026, 10:16 PM
lrt's friend lrt's friend is online now
Registered User
 
Join Date: Dec 2006
Posts: 12,601
Quote:
Originally Posted by J.OT13 View Post
Well yes, outside rush hour for sure. For better or worse, it is designed for commuters in mind, and if the thousands of people on the 174 see the train going faster than them, then it could convince them to go to take the train next time.

The only stretches of the O-Train that might be used all day by people who chose transit over car at all times will be Algonquin to Hurdman and Bayview to Carleton. The rest of the system will be heavily commuter focused.
For Line 2, it will be Bayview to South Keys. Traffic is pretty even going north and south from Carleton. South of South Keys, it is sadly mostly park n ride or kiss n ride commuters because of how badly we designed the bus transfers.
Reply With Quote
     
     
  #1519  
Old Posted Jan 15, 2026, 3:04 PM
AuxTown's Avatar
AuxTown AuxTown is offline
Registered User
 
Join Date: Apr 2006
Location: Ottawa, Canada
Posts: 4,552
What is the delay here??? The many return to work mandates for downtown workers has resulted in terrible traffic coming in from the east (luckily I come from the west). This would be a perfect time to roll out our shiny new trains from the far depths of Orleans right downtown but it's radio silence regarding a testing schedule :-(
Reply With Quote
     
     
  #1520  
Old Posted Jan 15, 2026, 4:56 PM
pattherat pattherat is offline
Registered User
 
Join Date: Nov 2018
Posts: 188
Quote:
Originally Posted by AuxTown View Post
What is the delay here??? The many return to work mandates for downtown workers has resulted in terrible traffic coming in from the east (luckily I come from the west). This would be a perfect time to roll out our shiny new trains from the far depths of Orleans right downtown but it's radio silence regarding a testing schedule :-(
And also zero detail on the deficiencies they said remained to be addressed. WHy not provide those details to the public? It’s what, over a month now since they said that? The line and stations have looked pretty sparse of workers every time I drive through there.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 7:51 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.