Old Posted Jan 17, 2025, 11:19 PM
Taeolas Taeolas is offline
Registered User
 
Join Date: Oct 2009
Location: Fredericton
Posts: 5,087
Quote:
Originally Posted by MonctonRad View Post
Work on the tower crane has now stopped entirely. Numerous pieces are on the ground waiting for assembly, but, nothing is being done.

WTF!?!? I know this is a government project, and, will not be complete until 2032. but still. Why erect the bottom half of the crane and then stop? What's the point of that???
Wonder if they discovered something wrong with the crane or the crane base.

I remember the crane that was at the project on Wagoneers Lane in Fredericton. They put the crane up for the second building, and then a week or two later (IIRC) they had to take it back down because something was wrong. Was a rather puzzling time.
Reply With Quote
     
     
  #62  
Old Posted Jan 22, 2025, 5:21 PM
MonctonGoldenTri MonctonGoldenTri is online now
Registered User
 
Join Date: Feb 2023
Location: Moncton
Posts: 279
The crane was completed this morning
Reply With Quote
     
     
  #63  
Old Posted Jan 22, 2025, 5:22 PM
MonctonRad's Avatar
MonctonRad MonctonRad is online now
Wildcats Rule!!
 
Join Date: Jun 2008
Location: Moncton NB
Posts: 41,193
Quote:
Originally Posted by MonctonGoldenTri View Post
The crane was completed this morning


I'll try to snap a picture soon.
__________________
Go 'Cats Go
Reply With Quote
     
     
  #64  
Old Posted Jan 22, 2025, 9:30 PM
MonctonRad's Avatar
MonctonRad MonctonRad is online now
Wildcats Rule!!
 
Join Date: Jun 2008
Location: Moncton NB
Posts: 41,193


A placeholder photo showing greater Moncton's newest tower crane.

__________________
Go 'Cats Go
Reply With Quote
     
     
  #65  
Old Posted Apr 26, 2025, 2:23 AM
MonctonRad's Avatar
MonctonRad MonctonRad is online now
Wildcats Rule!!
 
Join Date: Jun 2008
Location: Moncton NB
Posts: 41,193
Photo of the tower crane at the ASEC site (CTV News)



A building permit for $112.1M has just been issued by the city for phase 2 of this project.
__________________
Go 'Cats Go
Reply With Quote
     
     
  #66  
Old Posted May 24, 2025, 4:02 PM
MonctonRad's Avatar
MonctonRad MonctonRad is online now
Wildcats Rule!!
 
Join Date: Jun 2008
Location: Moncton NB
Posts: 41,193
They were busy pouring concrete for the basement foundation the other week.
__________________
Go 'Cats Go
Reply With Quote
     
     
  #67  
Old Posted Jun 19, 2025, 4:23 PM
Mr_Me Mr_Me is offline
Registered User
 
Join Date: Feb 2023
Posts: 10
Tenders for the trades are out
Reply With Quote
     
     
  #68  
Old Posted Jul 23, 2025, 4:06 PM
MonctonRad's Avatar
MonctonRad MonctonRad is online now
Wildcats Rule!!
 
Join Date: Jun 2008
Location: Moncton NB
Posts: 41,193
Quote:
Originally Posted by MonctonRad View Post
They were busy pouring concrete for the basement foundation the other week.
Foundation work now appears complete. It's great to finally see some progress on this significant development!
__________________
Go 'Cats Go
Reply With Quote
     
     
  #69  
Old Posted Jul 28, 2025, 12:31 PM
MonctonRad's Avatar
MonctonRad MonctonRad is online now
Wildcats Rule!!
 
Join Date: Jun 2008
Location: Moncton NB
Posts: 41,193


Reinforced structural support columns for the main floor are now being constructed and are visible as you drive by on Wheeler Blvd.
__________________
Go 'Cats Go
Reply With Quote
     
     
  #70  
Old Posted Jul 29, 2025, 12:55 AM
EnvisionSaintJohn's Avatar
EnvisionSaintJohn EnvisionSaintJohn is online now
New Brunswick, Canada ⛵️
 
Join Date: Apr 2023
Location: Canada's first City 🍁🌊
Posts: 4,015
Will this project have a "science centre" component open to the public?

That's what I assumed this place was, but I guess it's more of a research centre with offices for government agencies etc?
__________________
Peace and Athabasca and Coppermine and Slave, And Yukon and Mackenzie—the highroads of the brave. Saskatchewan, Assiniboine, the Bow and the Qu'Appelle, And many a prairie river whose name is like a spell. They rumor through the twilight at the edge of the unknown, "There's a message waiting for you, and a kingdom all your own. — Bliss Carman
Reply With Quote
     
     
  #71  
Old Posted Jul 29, 2025, 2:26 AM
MonctonRad's Avatar
MonctonRad MonctonRad is online now
Wildcats Rule!!
 
Join Date: Jun 2008
Location: Moncton NB
Posts: 41,193
Quote:
Originally Posted by EnvisionSaintJohn View Post
Will this project have a "science centre" component open to the public?

That's what I assumed this place was, but I guess it's more of a research centre with offices for government agencies etc?
It is primarily a multi-agency government research facility, but, there is a large lobby where they will have a whale skeleton suspended from the rafters, and presumably a small exhibit space of some kind. There will also be a lecture hall on the ground level as well, so, there may be some educational events available to the general public too. This is partially speculative, but, the lobby will at least be open to the public.
__________________
Go 'Cats Go
Reply With Quote
     
     
  #72  
Old Posted Aug 15, 2025, 12:58 PM
Mr_Me Mr_Me is offline
Registered User
 
Join Date: Feb 2023
Posts: 10
Quote:
Originally Posted by MonctonRad View Post
It is primarily a multi-agency government research facility, but, there is a large lobby where they will have a whale skeleton suspended from the rafters, and presumably a small exhibit space of some kind. There will also be a lecture hall on the ground level as well, so, there may be some educational events available to the general public too. This is partially speculative, but, the lobby will at least be open to the public.
It looks like all of this will be in the second phase. First phase which is currently being built seems to only have research labs and offices throughout the building.
Reply With Quote
     
     
  #73  
Old Posted Oct 8, 2025, 3:48 AM
MonctonRad's Avatar
MonctonRad MonctonRad is online now
Wildcats Rule!!
 
Join Date: Jun 2008
Location: Moncton NB
Posts: 41,193
They are finally beginning work on the second level of the expansion to the ASEC.

No wonder construction isn't expected to be finished until 2031!!!
__________________
Go 'Cats Go
Reply With Quote
     
     
  #74  
Old Posted Oct 8, 2025, 12:59 PM
darkharbour darkharbour is offline
Registered User
 
Join Date: Jan 2021
Posts: 832
Quote:
Originally Posted by MonctonRad View Post
They are finally beginning work on the second level of the expansion to the ASEC.

No wonder construction isn't expected to be finished until 2031!!!
Glad the NB Museum isn't the only large project in the province whose completion date seems very far on the horizon.
Reply With Quote
     
     
  #75  
Old Posted Oct 8, 2025, 2:34 PM
irisheyes irisheyes is offline
Registered User
 
Join Date: Jul 2025
Location: Saint John, New Brunswick
Posts: 78
Quote:
Originally Posted by MonctonRad View Post
Construction Begins on the New $700M Atlantic Science Enterprise Centre
https://tj.news/times-and-transcript/102142643 (paywall)



The article states that the tower crane will soon be installed. Actual construction of the new north wing of the facility won't begin until spring on next year.

The ceremonial groundbreaking was today.

The ultimate price tag includes all the scientific research equipment that the centre will be festooned with. $325M in construction contracts have already been issued.

The spending. How on earth was this not a scandal? I realize this is likely the wrong crowd - but this project smells fishy. Or should I say porky.
Reply With Quote
     
     
  #76  
Old Posted Oct 8, 2025, 3:33 PM
MonctonRad's Avatar
MonctonRad MonctonRad is online now
Wildcats Rule!!
 
Join Date: Jun 2008
Location: Moncton NB
Posts: 41,193
Quote:
Originally Posted by irisheyes View Post
The spending. How on earth was this not a scandal? I realize this is likely the wrong crowd - but this project smells fishy. Or should I say porky.
You think this is expensive? You should see the price tag of the new prison hospital to be built at the Dorchester Penitentiary......
__________________
Go 'Cats Go
Reply With Quote
     
     
  #77  
Old Posted Nov 17, 2025, 7:27 PM
MonctonRad's Avatar
MonctonRad MonctonRad is online now
Wildcats Rule!!
 
Join Date: Jun 2008
Location: Moncton NB
Posts: 41,193
Structural support elements for the third floor of the ASEC expansion project on Universite Avenue are starting to go up.
__________________
Go 'Cats Go
Reply With Quote
     
     
  #78  
Old Posted Dec 28, 2025, 4:23 AM
MonctonRad's Avatar
MonctonRad MonctonRad is online now
Wildcats Rule!!
 
Join Date: Jun 2008
Location: Moncton NB
Posts: 41,193
Now working on the fourth level of the ASEC expansion wing.
__________________
Go 'Cats Go
Reply With Quote
     
     
  #79  
Old Posted Feb 18, 2026, 5:08 PM
MonctonRad's Avatar
MonctonRad MonctonRad is online now
Wildcats Rule!!
 
Join Date: Jun 2008
Location: Moncton NB
Posts: 41,193
There is a proposal before PAC to allow the old MHS sports field to be used as a staging area in support of the construction of the ASEC.
__________________
Go 'Cats Go
Reply With Quote
     
     
  #80  
Old Posted Feb 19, 2026, 6:04 PM
BlackYear's Avatar
BlackYear BlackYear is offline
Registered User
 
Join Date: Jan 2009
Posts: 1,280
Quote:
Originally Posted by MonctonRad View Post
There is a proposal before PAC to allow the old MHS sports field to be used as a staging area in support of the construction of the ASEC.
Let me guess.
- Brand new asphalt resurfacing with proper base layer with new access road from Church st.
- Brand new perimeter fencing with barbwire, electronic surveillance, 8 dobermanns dogs specifically trained for ASEC, and the most sophisticated access gate known to man.
- New golden driveway from staging area to construction zone with 4 trailers along the way in case someone needs to go to the washroom, have a break, and rest.
- 20ft levee flood wall along Halls Creek to prevent the possibility of a major flood to the staging area.

And it wouldn't surprise me to see a magical dome covering the whole staging area in case of rain.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Atlantic Provinces
Forum Jump



Forum Jump


All times are GMT. The time now is 9:18 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.