Crews Prepare for Historic Concrete Pour at The Residences at 1428 Brickell on September 19
https://floridiandevelopment.com/crews-p...dences-at-1428-brickell-on-september-19/
Quote:
Crews behind 1428 Brickell are preparing for a historic milestone. On September 19, a massive foundation pour will begin at 8 p.m., led by C & C Concrete Pumping. With Capform as shell contractor, UES handling concrete testing, and Coastal Construction serving as general contractor, the team will pump an estimated 13,000 cubic yards of concrete into place.
The operation is expected to last 30 continuous hours, supported by five concrete pumps working simultaneously. Reinforcement steel is already in place, setting the stage for one of the largest foundation pours in Miami’s history. Comparable pours include the foundations of the Aston Martin Residences, Panorama Tower, and the Waldorf Astoria Miami, all of which exceeded 10,000 cubic yards.
|
|