Originally Posted by Orlando
So, I heard that Populous with MHTN won the rfp for the Salt Palace redo. Can anyone confirm that and dig up anything online about it?
|
What were you looking to find out? I have access to the actual RFP that was put out, but you'd have to make a public records request to get access to their submission.
Here's some of the detail of the RFP:
III. PROJECT DESCRIPTION
A. General Project Description:
1. The Architect services required in this RFP includes the site location, feasibility study, due diligence, programming, demolition, design and construction administration for the partial demolition and rebuild of the Salt Palace Convention Center (SPCC), AH back of house demolition and rebuild and/or other areas impacted by the SPCC, and the Visual Art Building/Utah Museum of Contemporary Art (UMOCA) demolition and re-build located in Salt Lake City, Utah, and the services outlined in Exhibits B, C, and D, all in accordance with the Contract Documents: a) SPCC Project Requirements – Exhibit B b) UMOCA Project Requirements – Exhibit C c) AH Project Requirements – Exhibit D
2. Architect’s services will be provided in two phases, described below. In all phases, the Architect will be required to coordinate with the Owner’s Consultants(s).
3. The Project is currently funded for the Phase 1 Programming phase. The County may conduct future phases of the work, without additional competitive solicitation, to provide Architectural/Engineering (A/E) services for design, and construction administration services, project closeout and warranty phases contingent upon funding. Alternatively, Request for Proposals Stage 1 - Qualifications to Provide Architectural / Engineering Services Page 7 County may opt instead to issue a solicitation(s) for A/E Services for additional phases of the work.
4. Once the scope of work is determined, the County may enter into an amendment for additional phases of the work contingent upon funding availability.
B. Project Budget
1. It is anticipated that the FLCC for Phase 2 of the Project will be approximately $900,000,000 to $1,100,000,000. This approximate amount is subject to modification during Stage 2 of the RFP in County’s sole discretion. If the County executes an amendment adding Phase 2, the County will specifically identify the FLCC which will be included in the Agreement pricing for Phase 2. The Proposer will not proceed with any work on Phase 2 until an amendment is executed adding the Fixed Fee.
Here's what they included as the project map: