Old Posted May 24, 2025, 3:56 AM
Spoofy Spoofy is offline
Registered User
 
Join Date: May 2016
Posts: 132
Quote:
Originally Posted by Djeffery View Post
The parking garage under what will become the next tower immediately south of the one that was just built. Right now there is no on site parking that I'm aware of for that tower
They have set up a temporary lot on the northeast portion of the property, but even then, that's maybe 30 spots or so.

Interestingly there does appear to be a crane pad at the northwest corner of the parking garage? Hopefully a good sign for potential future development of these lands.
Reply With Quote
     
     
  #302  
Old Posted May 24, 2025, 6:13 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,327
I suspect if we see another tower it will be on the east half of the parking lot in the future. The size of the footing foundations they are building now for the underground parking don't look large enough to support a 35s future tower. Maybe a building half that size if they decide to eventually build it.
Reply With Quote
     
     
  #303  
Old Posted May 24, 2025, 9:21 PM
Djeffery's Avatar
Djeffery Djeffery is online now
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 6,311
Quote:
Originally Posted by Spoofy View Post
They have set up a temporary lot on the northeast portion of the property, but even then, that's maybe 30 spots or so.

Interestingly there does appear to be a crane pad at the northwest corner of the parking garage? Hopefully a good sign for potential future development of these lands.
I suspect if I did see that lot, I probably assumed it was construction workers, as I only ever go by there in the daytime.
Reply With Quote
     
     
  #304  
Old Posted Jun 4, 2025, 11:26 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,327
Forming for the northern third of the L2 floor slab now well underway with good progress of the L2 walls and posts pours on the south end. Forming for the L3 to L2 ramp progressing well.
Reply With Quote
     
     
  #305  
Old Posted Jun 25, 2025, 4:28 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,327
They have now poured the L2 floor slab and the L3 to L2 parking ramp. Have around 60% of the L2 walls and posts now poured. Have got forming for the L1 floor slab on the south end of the pit now installed, waiting steel rebar installation next.
Reply With Quote
     
     
  #306  
Old Posted Jul 16, 2025, 5:02 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,327
They have now poured about 2/3rds of the L1 floor slab on the south side of the pit. Even have a couple of L1 posts now poured and others formed. They have also now poured the L2 to L1 parking ramp. Still have some of the last few sections of L2 walls to finish forming and pouring on the north end of the pit.
Reply With Quote
     
     
  #307  
Old Posted Jul 30, 2025, 12:32 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,327
They have now poured the remaining L1 floor slab on the north end of the pit. Forming and pouring of L1 walls and posts progressing on the south end.
Reply With Quote
     
     
  #308  
Old Posted Jul 30, 2025, 6:22 PM
ssiguy ssiguy is offline
Registered User
 
Join Date: Mar 2006
Location: White Rock BC
Posts: 11,964
I don't get it. Are you saying they have already the base of the 2nd building?
Reply With Quote
     
     
  #309  
Old Posted Jul 30, 2025, 9:38 PM
Djeffery's Avatar
Djeffery Djeffery is online now
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 6,311
Quote:
Originally Posted by ssiguy View Post
I don't get it. Are you saying they have already the base of the 2nd building?
Who knows when they are actually going to build the building itself but they have been building the underground parking garage that will be used by the new just completed building next door.
Reply With Quote
     
     
  #310  
Old Posted Jul 30, 2025, 11:48 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,327
It's doesn't appear that they will build a tower above this 3 level underground parking garage. The original proposal for 2 towers of 35s and 32s is I suspect history. They may well build a 2nd tower on the east side of the lot or partner or sell it off to another developer for a future project.
Reply With Quote
     
     
  #311  
Old Posted Aug 7, 2025, 7:47 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,327
Forming for the ground floor slab has started on the south end of the pit. Progressing on the L1 wall and post forming and pours.
Reply With Quote
     
     
  #312  
Old Posted Aug 24, 2025, 2:12 AM
ssiguy ssiguy is offline
Registered User
 
Join Date: Mar 2006
Location: White Rock BC
Posts: 11,964
I went by the site yesterday {yes I was in London!} and the whole site looks pretty large and under construction. It seems like a lot of work and money spent for a garage which is just replacing a parking lot.
Reply With Quote
     
     
  #313  
Old Posted Aug 26, 2025, 4:08 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,327
Doing the ground floor slab pour on the south third of the parking garage today. Concrete pump truck and parade of cement trucks. Lots of L1 wall and post forming yet to do as well as the forming for the L1 to ground parking ramp.
Reply With Quote
     
     
  #314  
Old Posted Aug 27, 2025, 2:27 AM
ssiguy ssiguy is offline
Registered User
 
Join Date: Mar 2006
Location: White Rock BC
Posts: 11,964
I don't get it. Why are they spending millions on a parking garage over a parking lot?
Reply With Quote
     
     
  #315  
Old Posted Aug 27, 2025, 10:34 AM
Djeffery's Avatar
Djeffery Djeffery is online now
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 6,311
Because at some point this will be the base of the next tower. I'm sure part of the thought process was by the time the parking levels were done, the market would be more favourable to building that next tower.
Reply With Quote
     
     
  #316  
Old Posted Aug 31, 2025, 7:47 PM
ssiguy ssiguy is offline
Registered User
 
Join Date: Mar 2006
Location: White Rock BC
Posts: 11,964
Well that kind of makes sense and it's cheaper to build it now than later. This bodes very well for the development going forward.
Reply With Quote
     
     
  #317  
Old Posted Sep 4, 2025, 6:40 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,327
They have now poured the ground floor slab in the middle section. None of the walls and posts have steel rebar above the slab where future walls and posts would be in a future building, so its not likely ever planned to happen. The eastern half of this parcel is undeveloped and may in the future see a high rise building but it may be years before that happens and may not even by Ayerswood that does it.
Reply With Quote
     
     
  #318  
Old Posted Sep 12, 2025, 12:13 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,327
They are now forming the parking ramp above ground walls. Forming for the remaining ground floor slab on the north end is well underway and should be poured very soon.
Reply With Quote
     
     
  #319  
Old Posted Sep 20, 2025, 1:00 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,327
Looks like they have now poured the ground floor slab on the northern third completing the ground floor slab. They have also now poured the walls of what appears to be a stairwell entrance along the King St side. Work continues on the parking ramp entrance above ground walls. Concrete work is wrapping up soon on this parking garage and would expect the tower crane to be removed shortly. Still no news on what they have decided to do on the eastern side of the remaining property. Will it be used as a surface parking lot for years to come or see a future building?
Reply With Quote
     
     
  #320  
Old Posted Sep 20, 2025, 3:41 AM
Snark Snark is offline
Registered User
 
Join Date: May 2006
Posts: 505
Quote:
Originally Posted by jammer139 View Post
Still no news on what they have decided to do on the eastern side of the remaining property. Will it be used as a surface parking lot for years to come or see a future building?
The number of parking spaces in the new structure might at least suggest what the future may hold.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 9:52 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.