  #741  
Old Posted Mar 19, 2025, 8:56 PM
bomberjet bomberjet is offline
Registered User
 
Join Date: Nov 2012
Location: Winnipeg
Posts: 16,357
Not everything is a scam you know..

Costs for sure have gone up. The original estimating probably not there. If you go back in this thread I'm pretty sure it was said that budget will surely be blown.

Some clarity on scope and costs would go along way for public support.
Reply With Quote
     
     
  #742  
Old Posted Mar 19, 2025, 8:59 PM
WinCitySparky's Avatar
WinCitySparky WinCitySparky is online now
Registered User
 
Join Date: Jan 2019
Posts: 2,414
Makes sense
Reply With Quote
     
     
  #743  
Old Posted Mar 19, 2025, 9:02 PM
bomberjet bomberjet is offline
Registered User
 
Join Date: Nov 2012
Location: Winnipeg
Posts: 16,357
I'm also not sure if PCL competitively bid this work. Or if they were single sources a la TNSE always does that.

PCL is notorious for driving for the cheapest possible thing in my experience. I can't see them blindly accepting for double triple dipping. But you never know.

That leaves SCO as the source for the scams if there's anything going on.
Reply With Quote
     
     
  #744  
Old Posted Mar 19, 2025, 9:14 PM
borkborkbork's Avatar
borkborkbork borkborkbork is offline
Registered User
 
Join Date: Jul 2014
Posts: 1,755
Quote:
Originally Posted by pegster View Post
I'm not exactly surprised. The retrofitting of a similar, albeit larger, old department store building (a Dayton's, later a Macy's) in Minneapolis has cost upwards of 375 million USD (and has had it's own issues: https://tcbmag.com/beleaguered-daytons-project-put-into-receivership/), but doesn't seem nearly as ambitious as what's planned for HBC.
The HBC building in Victoria BC building was "$200-300M" back in 2010-15.

https://merrickarch.com/work/bay-site-redevelopment/

At 655,000 square feet for a project that involves restoration and modernization of a complex heritage building... it feels like under $200 psf (the original $130M estimate) was always a laughable number...
Reply With Quote
     
     
  #745  
Old Posted Mar 19, 2025, 10:25 PM
pspeid's Avatar
pspeid pspeid is offline
Registered User
 
Join Date: Aug 2018
Posts: 2,645
Of course this still leaves the question of where the extra money will come from? Personally I still think this is such a high-profile project that it's not going to be left high and dry. Governments, even those without extra cash lying around, seem to have ways to find financing. I suppose there might even be overtures made to other First Nations organizations, but again, who has the cash? It might be possible to solicit from any community-minded private entities who would like their name attached to a positive story about "reconciliation in action". It'll be interesting to see how this goes.
__________________
"Opinion is really the lowest form of intelligence"-Bill Bullard

"Naysayers are always predicting the present"-Anon.

"Rudeness is the weak man's imitation of strength"-Eric Hoffer
Reply With Quote
     
     
  #746  
Old Posted Mar 19, 2025, 10:55 PM
OTA in Winnipeg OTA in Winnipeg is offline
Registered User
 
Join Date: Mar 2016
Location: Silver Heights
Posts: 1,798
I'll be surprised if this comes in under 600M.
Reply With Quote
     
     
  #747  
Old Posted Mar 19, 2025, 10:57 PM
WinCitySparky's Avatar
WinCitySparky WinCitySparky is online now
Registered User
 
Join Date: Jan 2019
Posts: 2,414
We should start a pool
Reply With Quote
     
     
  #748  
Old Posted Mar 19, 2025, 11:27 PM
Labroco's Avatar
Labroco Labroco is offline
Registered User
 
Join Date: Jan 2014
Location: Toronto
Posts: 844
I think they should deal the with the atrium and major work of three floors at this time and complete the rest in a phase 2. This will allow for the project to be completed sooner.


The idea of it dragging on for years is discerning anyway one looks at it. Deer in the headlights!
Reply With Quote
     
     
  #749  
Old Posted Mar 20, 2025, 1:08 PM
Biff's Avatar
Biff Biff is offline
What could go wrong?
 
Join Date: Jun 2004
Location: Winnipeg
Posts: 9,933
IMO this has nothing to do with cost escalation. This was a terribly low budget from the start that everyone knew was not accurate. It was so low it was laughable. Before the project was even announced, most of the people I spoke with about the possibility of redeveloping The Bay thought a $300-$400m budget was what it would take.

I am not really sure where they turn to make up that massive amount.
__________________
"But a city can be smothered by too much reverence for its past. The skyline must keep acquiring new peaks, because the day we consider it complete and untouchable is the day the city begins to die." - Justin Davidson - May 2010 Issue of New York
Reply With Quote
     
     
  #750  
Old Posted Mar 20, 2025, 1:10 PM
FactaNV FactaNV is offline
Registered User
 
Join Date: Sep 2023
Posts: 2,378
Quote:
Originally Posted by Biff View Post
IMO this has nothing to do with cost escalation. This was a terribly low budget from the start that everyone knew was not accurate. It was so low it was laughable. Before the project was even announced, most of the people I spoke with about the possibility of redeveloping The Bay thought a $300-$400m budget was what it would take.

I am not really sure where they turn to make up that massive amount.
It's not like SCO doesn't have revenue streams, for example South Beach casino. They'll probably have to find their own moolah.
Reply With Quote
     
     
  #751  
Old Posted Mar 20, 2025, 2:06 PM
drew's Avatar
drew drew is offline
the first stamp is free
 
Join Date: Feb 2004
Location: Hippyville, Winnipeg
Posts: 8,928
Quote:
Originally Posted by Biff View Post
IMO this has nothing to do with cost escalation. This was a terribly low budget from the start that everyone knew was not accurate. It was so low it was laughable. Before the project was even announced, most of the people I spoke with about the possibility of redeveloping The Bay thought a $300-$400m budget was what it would take.

I am not really sure where they turn to make up that massive amount.
Who's the architect on this job?

Usually its their job to organize and communicate budget realities to the clients/developers.
Reply With Quote
     
     
  #752  
Old Posted Mar 20, 2025, 2:26 PM
bomberjet bomberjet is offline
Registered User
 
Join Date: Nov 2012
Location: Winnipeg
Posts: 16,357
Shots fired haha
Reply With Quote
     
     
  #753  
Old Posted Mar 20, 2025, 4:31 PM
cllew cllew is offline
Registered User
 
Join Date: Feb 2012
Posts: 4,843
Quote:
Originally Posted by drew View Post
Who's the architect on this job?

Usually its their job to organize and communicate budget realities to the clients/developers.
Number 10 architectural is running the project from what I see online.
Reply With Quote
     
     
  #754  
Old Posted Mar 20, 2025, 4:40 PM
cllew cllew is offline
Registered User
 
Join Date: Feb 2012
Posts: 4,843
Quote:
Originally Posted by FactaNV View Post
It's not like SCO doesn't have revenue streams, for example South Beach casino. They'll probably have to find their own moolah.
I think there are 6 indigenous casino's in Manitoba, I don't know if they are all pay into one profit pool that could be tapped or each one would have to contribute a portion of their profits separately.

Some of the northern ones may not want to pay into a SCO project.
Reply With Quote
     
     
  #755  
Old Posted Mar 20, 2025, 5:12 PM
Wpg_Guy's Avatar
Wpg_Guy Wpg_Guy is online now
Moderator
 
Join Date: Aug 2002
Location: Winnipeg, Manitoba
Posts: 8,476
The SCO briefly mentions the funding gap in this CBC article:

Quote:
Daniels said the SCO plans to raise the remainder of the funding for the project.

"We will get there, and I guarantee that our team is well-prepared for that," he said.
https://www.cbc.ca/amp/1.7487724
__________________
Winnipeg Act II - April 2024

Winnipeg Developments

In The Future Every Building Will Be World-Famous For Fifteen Minutes.
Reply With Quote
     
     
  #756  
Old Posted Mar 20, 2025, 8:29 PM
trueviking's Avatar
trueviking trueviking is offline
surely you agree with me
 
Join Date: Sep 2004
Location: winnipeg
Posts: 15,076
Quote:
Originally Posted by drew View Post
Who's the architect on this job?

Usually its their job to organize and communicate budget realities to the clients/developers.
Its usually the quantity surveyor or construction manager (or both) that creates budgets....architects draw, they don't budget....they respond to budgets.

The project has been budgeted from day one and the client has always been aware of the costs....they have been working in lock step with CMHC to develop a workable pro-forma.

Developers can announce whatever they want to the public. Don’t believe any numbers you hear, ever. No developer is ever showing their real cards to the media.

Last edited by trueviking; Mar 21, 2025 at 12:46 AM.
Reply With Quote
     
     
  #757  
Old Posted Mar 21, 2025, 6:39 PM
wags_in_the_peg's Avatar
wags_in_the_peg wags_in_the_peg is offline
Registered User
 
Join Date: Oct 2006
Location: Winnipeg, MB
Posts: 3,855
Quote:
Originally Posted by trueviking View Post
Its usually the quantity surveyor or construction manager (or both) that creates budgets....architects draw, they don't budget....they respond to budgets.

The project has been budgeted from day one and the client has always been aware of the costs....they have been working in lock step with CMHC to develop a workable pro-forma.

Developers can announce whatever they want to the public. Don’t believe any numbers you hear, ever. No developer is ever showing their real cards to the media
.
^interesting, i feel theres more to that story!
__________________
just an ordinary Prairie Boy who loves to be in the loop on what is going on
Reply With Quote
     
     
  #758  
Old Posted Apr 11, 2025, 6:29 PM
Biff's Avatar
Biff Biff is offline
What could go wrong?
 
Join Date: Jun 2004
Location: Winnipeg
Posts: 9,933
From LinkedIn - Southern Chiefs'​ Organization (SCO)

__________________
"But a city can be smothered by too much reverence for its past. The skyline must keep acquiring new peaks, because the day we consider it complete and untouchable is the day the city begins to die." - Justin Davidson - May 2010 Issue of New York
Reply With Quote
     
     
  #759  
Old Posted Apr 11, 2025, 6:32 PM
drew's Avatar
drew drew is offline
the first stamp is free
 
Join Date: Feb 2004
Location: Hippyville, Winnipeg
Posts: 8,928
^ looks like there is a built-up wood framed roof (probably sloped) on top of the flat concrete roof deck.

Seems like we are starting to see at least the north perimeter outline of the atrium.

I assume all those white bags are demo'd material waiting to get craned down?
Reply With Quote
     
     
  #760  
Old Posted Apr 11, 2025, 6:35 PM
cllew cllew is offline
Registered User
 
Join Date: Feb 2012
Posts: 4,843
Quote:
Originally Posted by drew View Post
^ looks like there is a built-up wood framed roof (probably sloped) on top of the flat concrete roof deck.

Seems like we are starting to see at least the north perimeter outline of the atrium.

I assume all those white bags are demo'd material waiting to get craned down?
Looks like there is a dump truck at the bottom by the crane foundation with some of the bags in its dump box.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Manitoba & Saskatchewan
Forum Jump



Forum Jump


All times are GMT. The time now is 1:42 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.