estimated cost $49 million
Estimated Construction - Fall 2025
Construction is anticipated to begin Fall 2025, with utility work anticipated to begin late Summer 2025
Construction will be a phased approach:
Phase one: Demolition and construction of the west side, Fall 2025 - Fall 2026
Phase two: Demolition and construction of the east side, Fall 2026 - Fall 2027*
Replacing the viaduct will provide a bridge that meets current design
standards, improves visibility for drivers, enhances connections for walking and
biking, stays within the existing footprint and will have a service life of
approximately 75 years. Current design includes:
● Two 11 ft lanes each direction
● 3 ft median
● 8 ft sidewalk each side
● Bike lane each direction in 10 ft shoulders