Quote:
Originally Posted by ecbin
I dig it - that setback (which I'm normally opposed to) really opens up the area (sure wish Burnaby could build like this). Looks great but such a shame that it has taken this many years to get approved. I've driven by that area a few times lately and it's just a bit sad now.
|
The initial rezoning application was submitted on November 14, 2023. It was revised in 2024 by 'shifting the towers further away from 10th Avenue, a reduced podium height, wrapping the retail space around the plaza edges, wider sidewalks along 10th Avenue, and adding a second underground parking entrance.' So it's been 16 months to process the rezoning, give the developer feedback on what needed to change to make it work better, receive the revised version, and get it to Council for approval. That's reasonably speedy for such a consequential project with a few things that needed to be sorted out with the design, and a fair amount of local opposition.