  #61  
Old Posted Jun 11, 2024, 8:31 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
No renders yet on their website.


https://www.tricar.com/locations/masonville/
Reply With Quote
     
     
  #62  
Old Posted Jul 2, 2024, 3:31 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
Tricar has now excavate the pit for whatever building they plan on eventually putting up here. No signs they have started the foundation as of yet and are probably waiting on permit for that work. Similarly they excavated the pit for the building they plan on Ridout St south a number of years ago and have not moved forward on that.
Reply With Quote
     
     
  #63  
Old Posted Aug 17, 2024, 4:49 PM
CanadianTalk's Avatar
CanadianTalk CanadianTalk is offline
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 1,304
A building permit was issued last month:

Reply With Quote
     
     
  #64  
Old Posted Aug 17, 2024, 9:02 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
Would not be surprised they are switching this to rental apartments from condo as the new build condo market is dead right now. Will be interesting to see renders for this much shorter building and how they orient it on the property.
Reply With Quote
     
     
  #65  
Old Posted Aug 24, 2024, 1:09 PM
CanadianTalk's Avatar
CanadianTalk CanadianTalk is offline
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 1,304
Just saw an ad for this on Facebook from Tricar.

They are marketing this as "The Grove" and yes they will be rentals

https://www.tricar.com/locations/thegrove/
Reply With Quote
     
     
  #66  
Old Posted Aug 29, 2024, 12:13 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
Tricar has been making progress with the foundation footings and are now putting in the rebar steel for a large floating raft slab foundation. Also appear to be getting the tower crane base ready. Should see a tower crane assembled very soon.
Reply With Quote
     
     
  #67  
Old Posted Sep 16, 2024, 7:52 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
Looks like they have now got all the structural steel rebar installed for the floating raft foundation slab. Just scheduling now for multiple concrete pump trucks and a steady parade of cement trucks to keep them fed with concrete to complete this massive pour.

Last edited by jammer139; Sep 16, 2024 at 11:59 PM.
Reply With Quote
     
     
  #68  
Old Posted Sep 20, 2024, 7:07 PM
CanadianTalk's Avatar
CanadianTalk CanadianTalk is offline
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 1,304
Here is an update from Tricar:

Big Day Tomorrow at The Grove Masonville! The site is prepped, and the crew is ready for a massive raft slab pour at 230 North Centre Road.

This massive concrete pour will total 4,500 cubic metres—the equivalent of 125 single-family home foundations—and will be completed in less than 15 hours. A fleet of 100 trucks will be in continuous operation, delivering 500 loads of concrete to the site.

A portion of Richmond Street will be closed for the day, and minor detours will be in place. Thank you for your patience.



Reply With Quote
     
     
  #69  
Old Posted Sep 21, 2024, 12:50 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
Reply With Quote
     
     
  #70  
Old Posted Sep 21, 2024, 7:09 PM
CanadianTalk's Avatar
CanadianTalk CanadianTalk is offline
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 1,304
Quote:
Originally Posted by jammer139 View Post
Here is a another pic of the site (from the article)

Reply With Quote
     
     
  #71  
Old Posted Sep 29, 2024, 8:00 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
Forming now started for the L2 walls in the NW corner of the pit and they already have some of the precast concrete L2 posts installed. Still using a mobile crane at this point with no signs of a tower crane being assembled as of yet.
Reply With Quote
     
     
  #72  
Old Posted Oct 11, 2024, 7:24 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
They have made good progress installing the L2 level precast concrete walls and posts and forming for the poured sections. Still no signs of a tower crane being setup as of yet.
Reply With Quote
     
     
  #73  
Old Posted Oct 27, 2024, 3:10 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
Work continues with the precast wall and post installs and the forming of the L2 level walls. Still using a mobile crane with no signs of a tower crane being setup for this 11s story building.
Reply With Quote
     
     
  #74  
Old Posted Nov 16, 2024, 1:11 AM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
Probably the last new tower crane of 2024 has finally gone up for Tricar's 11s project. The L2 walls and posts are nearing completion and we will likely see the L1 precast floor slabs start being installed soon as well as the parking ramp. I believe this is only the 5th new tower crane to go up in 2024. Big difference from just a few years ago when I believe London had 20 tower cranes standing compared to the 11 tower cranes currently.
Reply With Quote
     
     
  #75  
Old Posted Nov 29, 2024, 3:53 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
Almost done with the L1 precast concrete floor slab installs and have started installing some of the L1 precast concrete walls along the north side. Also have started backfilling the L2 walls along the Richmond St side. This building is setback against the hillside so will have extra challenges to deal with water runoff and drainage. Will be interesting to see how they design the SE corner driveway entrance and pedestrian access to the building with the low point being the SE corner. Not sure why there are no renders posted anywhere yet?
Reply With Quote
     
     
  #76  
Old Posted Jan 17, 2025, 7:45 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
Now installing what some might call the 3rd floor walls in the NW corner. Although because of the slope of the hill this may actually be the first residential floor given they say there are 2 levels of underground parking. Would be interesting to see renders of this new Tricar building to get a sense of the footprint of this building.
Reply With Quote
     
     
  #77  
Old Posted Jan 29, 2025, 11:32 PM
CanadianTalk's Avatar
CanadianTalk CanadianTalk is offline
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 1,304
Tricar recently posted a rendering on their website: https://www.tricar.com/locations/thegrove/


Reply With Quote
     
     
  #78  
Old Posted Jan 30, 2025, 4:46 AM
GreatTallNorth2 GreatTallNorth2 is offline
Registered User
 
Join Date: May 2006
Posts: 1,772
Quote:
Originally Posted by CanadianTalk View Post
Tricar recently posted a rendering on their website: https://www.tricar.com/locations/thegrove/


Nothing wonderful but could be worse.
Reply With Quote
     
     
  #79  
Old Posted Jan 30, 2025, 1:19 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
Good to see render finally. Looks like this will have an L shaped footprint above the podium base overlooking the roads.
Reply With Quote
     
     
  #80  
Old Posted Feb 7, 2025, 6:01 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,517
Nearly finished installing the 3rd floor? precast floor slabs. Some of the window modules are now installed as well in the podium of this 11s building.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 8:13 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.