Quote:
Originally Posted by jollyburger
|
Yes, I believe the north-westernmost section (The Superstore-fronting parking lot) will be the first one to get the greenlight since it's the one that requires the least heavy-lifting (red-tape, logistics,...etc).
The southwesterly-most section, I don't believe will happen any time soon unless they can come up with a plan for an alternate Bus loop location that's acceptable to both the City and Translink who are both against relocating it at all.
The parkade structure adjacent to the Metro Office towers to their east is also possible but that one would likely create a lot more disruption for the office towers and the mall tenants on that side of the mall seeing as it also serves as the loading bay junction for that side of the mall.
It also encompasses the Walmart, and the T&T store downstairs and they both have leases running into the 2050's. (Yes, leases can be terminated by mutual consent, but Ivanhoe would likely have to provide a considerable payout to both in order to do so)
The north-eastern section neighbouring the Concord towers will likewise most likely be dependent on when the lease for The Bay runs out.
And it too will come with logistical challengs as the main Food Court will likely have to close down too.
Which brings us back to the Superstore parking lot and the fact that there's already construction happening on that side of Kingsway (with more coming too once phase 2 of Concord's project goes into development in additionto Citizen across the road that's already under construction.), should in my opinion make it the no-brainer 'Phase 1' for ths grand development.
Lots of projects this year all over the various municipalities seem to be coming out of the Inflation crisis-fueled limbo that they were in over the past several years. So hopefully it shouldn't be long before we get some news on this one as well sometime this year.