  #3201  
Old Posted Jan 13, 2025, 9:25 PM
AuxTown's Avatar
AuxTown AuxTown is offline
Registered User
 
Join Date: Apr 2006
Location: Ottawa, Canada
Posts: 4,634
Quote:
Originally Posted by OCCheetos View Post
They are transported by truck. https://x.com/OC_Transpo/status/1869426197836222623

There are three(?) trains at Moodie now.
This is awesome! It's been a long wait, but the last bit will be really exciting when trains start zipping down the track for testing.

Are all the stations substantially completed? Which need the most work?

Reply With Quote
     
     
  #3202  
Old Posted Jan 14, 2025, 2:21 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,961
Quote:
Originally Posted by AuxTown View Post
This is awesome! It's been a long wait, but the last bit will be really exciting when trains start zipping down the track for testing.

Are all the stations substantially completed? Which need the most work?
Testing should start this year in the West. Don't remember the date, but I think it will be by summer.

Most stations are well advanced, not far behind the East honestly. Westboro is the only one that's further behind, but that was by design as they wanted to keep the Scott Street trench open as long as possible. Last I checked, concrete work was nearly done, so steel shouldn't be far behind.
Reply With Quote
     
     
  #3203  
Old Posted Jan 14, 2025, 2:44 PM
OTSkyline OTSkyline is offline
Registered User
 
Join Date: Jun 2012
Posts: 2,825
Lincoln Fields has looked substantially completed for many many months now (maybe 6+) but have noticed since XMAS that they have even installed some of the last minute things like signage & perhaps even fare machines?
Reply With Quote
     
     
  #3204  
Old Posted Jan 14, 2025, 3:41 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,961
Quote:
Originally Posted by OTSkyline View Post
Lincoln Fields has looked substantially completed for many many months now (maybe 6+) but have noticed since XMAS that they have even installed some of the last minute things like signage & perhaps even fare machines?
They want Lincoln Fields done first in the west. It's sort of their test station, or something to that effect.
Reply With Quote
     
     
  #3205  
Old Posted Jan 31, 2025, 1:38 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,961
Ward 8 Presentation for last week:

Video Link


We got a shot of the platform level at Algonquin.

Reply With Quote
     
     
  #3206  
Old Posted Feb 4, 2025, 11:10 PM
AuxTown's Avatar
AuxTown AuxTown is offline
Registered User
 
Join Date: Apr 2006
Location: Ottawa, Canada
Posts: 4,634
moving to the Stage 3 thread
Reply With Quote
     
     
  #3207  
Old Posted Feb 4, 2025, 11:27 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by J.OT13 View Post
Ward 8 Presentation for last week:

Video Link


We got a shot of the platform level at Algonquin.

Interesting. So they are using the fake metal ceilings on the west section too, even though at moodie it looks like they have the stage 2 style wood slats. Maybe it's just at certain stations, or it isn't what it looks like in the Moodie picture.

I kind of prefer the ceiling they used on the trillium line stations though, it's more convincing.

Reply With Quote
     
     
  #3208  
Old Posted Feb 5, 2025, 10:31 PM
AuxTown's Avatar
AuxTown AuxTown is offline
Registered User
 
Join Date: Apr 2006
Location: Ottawa, Canada
Posts: 4,634
Am I naive to think that they are developing really well on the West extension and might actually deliver something on time? The tracks are being laid, the vehicles are on site and the stations are all really close to complete. Do you think it will open in 2026? Early 2027? Can't wait to see some trains testing down the line.
Reply With Quote
     
     
  #3209  
Old Posted Feb 5, 2025, 11:56 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by AuxTown View Post
Am I naive to think that they are developing really well on the West extension and might actually deliver something on time? The tracks are being laid, the vehicles are on site and the stations are all really close to complete. Do you think it will open in 2026? Early 2027? Can't wait to see some trains testing down the line.
I have endless faith in our city to mess things up
Reply With Quote
     
     
  #3210  
Old Posted Mar 29, 2025, 4:25 PM
Admiral Nelson Admiral Nelson is offline
Registered User
 
Join Date: Jun 2009
Posts: 519
March 17 update to transit committee on the western extension:

https://youtu.be/sjYfFVsRi-w?t=11895
Reply With Quote
     
     
  #3211  
Old Posted Mar 31, 2025, 1:45 PM
OTSkyline OTSkyline is offline
Registered User
 
Join Date: Jun 2012
Posts: 2,825
Construction seems to be advancing quite rapidly and they state track work and most station work should be completed in 2025.

With that being said, they also state goal is to "handover to the City at the end of 2026" with trial running and start of operation in 2027.

This is the first time I hear 2027 being mentioned... this is disappointing.
Reply With Quote
     
     
  #3212  
Old Posted Mar 31, 2025, 3:00 PM
lrt's friend lrt's friend is offline
Registered User
 
Join Date: Dec 2006
Posts: 12,797
These rail systems are so complex. It takes forever to test and debug them for safe operations. How times have changed. Reading back to when electric streetcars were introduced and it was crazy how fast it was from laying track until opening for service even using public streets. It might take 3 to 6 months. Construction moved fast and the much simpler streetcars seem to work with few problems almost immediately.
Reply With Quote
     
     
  #3213  
Old Posted Mar 31, 2025, 3:10 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,961
Quote:
Originally Posted by OTSkyline View Post
Construction seems to be advancing quite rapidly and they state track work and most station work should be completed in 2025.

With that being said, they also state goal is to "handover to the City at the end of 2026" with trial running and start of operation in 2027.

This is the first time I hear 2027 being mentioned... this is disappointing.
Pretty much what I expected. Not bad at all if it comes to be.
Reply With Quote
     
     
  #3214  
Old Posted Mar 31, 2025, 5:36 PM
AuxTown's Avatar
AuxTown AuxTown is offline
Registered User
 
Join Date: Apr 2006
Location: Ottawa, Canada
Posts: 4,634
Quote:
Originally Posted by OTSkyline View Post
Construction seems to be advancing quite rapidly and they state track work and most station work should be completed in 2025.

With that being said, they also state goal is to "handover to the City at the end of 2026" with trial running and start of operation in 2027.

This is the first time I hear 2027 being mentioned... this is disappointing.
It will give them some time to work out the kinks before we move the Sens to Lebreton and start relying on the lines for all of our big events.
Reply With Quote
     
     
  #3215  
Old Posted Mar 31, 2025, 5:39 PM
Dengler Avenue's Avatar
Dengler Avenue Dengler Avenue is offline
Road Engineer Wannabe
 
Join Date: Sep 2017
Location: Côté Ouest de la Rivière des Outaouais
Posts: 8,682
Here’s hoping that OCTranspo will also use that time to figure out how to adjust the routing and frequency of the Kanata buses.
__________________
My Proposal of TCH Twinning in Northern Ontario
Disclaimer: Most of it is pure pie in the sky, so there's no need to be up in the arm about it.
Reply With Quote
     
     
  #3216  
Old Posted Mar 31, 2025, 7:44 PM
DarthVader_1961 DarthVader_1961 is offline
Registered User
 
Join Date: Jun 2009
Posts: 474
Wonder if the go slow orders will be resolved before 2027?
Reply With Quote
     
     
  #3217  
Old Posted Apr 1, 2025, 8:06 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,961
Quote:
Originally Posted by DarthVader_1961 View Post
Wonder if the go slow orders will be resolved before 2027?
They'd better, otherwise it will be nearly 2 hours to get from Moodie to Trim.
Reply With Quote
     
     
  #3218  
Old Posted Apr 2, 2025, 2:06 PM
lrt's friend lrt's friend is offline
Registered User
 
Join Date: Dec 2006
Posts: 12,797
Quote:
Originally Posted by J.OT13 View Post
They'd better, otherwise it will be nearly 2 hours to get from Moodie to Trim.
If at both ends you can walk to your destination. Well, there is also Uber. Door to door that might be 30 minutes., but as others have said, at least the 2 hours is predictable.
Reply With Quote
     
     
  #3219  
Old Posted Apr 14, 2025, 1:15 PM
sseguin sseguin is offline
Registered User
 
Join Date: Aug 2018
Posts: 315
Tracking the Progress: Ottawa’s O-Train Stage 2 Western Extension - April 2025

Rail Fans Canada takes you trackside for an in-depth update on Ottawa’s expanding LRT system. In this April 2025 video, we cover the latest construction progress on the O-Train Stage 2 West Extension, stretching from Tunney's Pasture Station to Algonquin and Moodie in the west..

Get a close-up look at station construction, trackwork, and what’s coming next as this vital light rail extension moves closer to completion. Whether you’re following the city’s transit evolution or just love all things rail, this is your go-to update for the O-Train West Extension.

Video Link
__________________
Rail Fans Canada - https://www.RailFans.ca
Reply With Quote
     
     
  #3220  
Old Posted Apr 17, 2025, 5:51 PM
Kitchissippi's Avatar
Kitchissippi Kitchissippi is offline
Busy Beaver
 
Join Date: Nov 2005
Location: Ottawa
Posts: 4,687
Kichi Zìbì station is one of those construction sites where you get really get a good look at what's happening.

Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 7:22 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.